Energy Projects Near You

Renewable energy projects in Bromley

10 solar, wind or battery projects of 150 kW or more are located in Bromley (REPD, July 2026 extract): 1 pending, 9 approved but not running, 0 operational and 0 refused.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects in the council area
1awaiting a decision
9approved, not running
0operational

How Bromley decides

Bromley has 8 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Projects in Bromley

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Layhams Roadbattery storagebattery storage250approved, not builtupdated Apr 2026Feb 2025granted Mar 2026Apr 2026
Biggin Hill Airport, Main Roadrooftop solarrooftop solar12under constructionupdated Dec 2023——Dec 2023
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
David Lloyd Leisure, Stanhope Groverooftop solarrooftop solar0.5approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023
The Spa, Beckenham Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2023Feb 2023granted Apr 2023May 2023
J Sainsbury, Walters Yardrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Apr 2026granted Jun 2026Jun 2026
Pavilion Leisure Centre, Kentish Wayrooftop solarrooftop solar0.2approved, not builtupdated Apr 2023Mar 2023granted Apr 2023Apr 2023
Croydon Roadrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023
Tesco Stores Limited, Edgington Wayrooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025
Bethlem Royal Hospital, Monks Orchard Road Solar Panels & Air Source Heat Pumpsrooftop solarrooftop solar—approved, not builtupdated Sep 2022May 2022granted Aug 2022Sep 2022
Bethlem Royal Hospital, Monks Orchard Roadrooftop solarrooftop solar—application submittedMay 2026——

Postcode districts in Bromley

DistrictProjects within 10 kmPendingApprovedOperational
BR1414291
BR2242210
BR3335240
BR4212190
BR5252220
BR6162130
BR7353241
SE20396290
TN169080

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Bromley by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.