Renewable energy projects in Eastbourne

11 solar, wind or battery projects of 150 kW or more are located in Eastbourne (REPD, July 2026 extract): 2 pending, 7 approved but not running, 2 operational and 0 refused.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects in the council area
2awaiting a decision
7approved, not running
2operational

How Eastbourne decides

Eastbourne has 8 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Projects in Eastbourne

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Suncoast Solar Farmsolar farmsolar farm20approved, not builtupdated Feb 2026Nov 2023granted Feb 2025Feb 2026
Suncoast Battery Storagebattery storagebattery storage5approved, not builtupdated Feb 2026Nov 2023granted Feb 2025Feb 2026
Eastbourne District General Hospital Energy Managementrooftop solarrooftop solar1.1operationalupdated Nov 2023——Nov 2023
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Broadwater Wayrooftop solarrooftop solar0.6application submittedupdated Jan 2025Aug 2024—Jan 2025
The David Lloyd Centrerooftop solarrooftop solar0.4application submitted may be out of dateupdated Jul 2023Jul 2023—Jul 2023
Morrisons, Hargreaves Roadrooftop solarrooftop solar0.3approved, not builtupdated Apr 2023Sep 2022granted Oct 2022Apr 2023
Tesco Lottbridge Droverooftop solarrooftop solar0.2operationalupdated Nov 2019Mar 2019granted Apr 2019Nov 2019
Finmere Roadbattery storagebattery storage0.2approved, not built may be out of dateupdated Jan 2023Oct 2022granted Dec 2022Jan 2023
Marshall Roadrooftop solarrooftop solar0.2approved, not builtupdated Jun 2023Mar 2023granted May 2023Jun 2023
Bannatynes Gyms, Edward Roadrooftop solarrooftop solar0.2approved, not builtupdated Jun 2024Jun 2024granted Jul 2024Jun 2024
Whittle Driverooftop solarrooftop solar0.1approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026

Postcode districts in Eastbourne

DistrictProjects within 10 kmPendingApprovedOperational
BN2016385
BN2115285
BN2217395
BN23193115

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Eastbourne by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.