Energy Projects Near You

Renewable energy projects in Enfield

19 solar, wind or battery projects of 150 kW or more are located in Enfield (REPD, July 2026 extract): 3 pending, 14 approved but not running, 1 operational and 1 refused. The council refused 1 of 16 decided applications (6%; UK 19%), with a median 8 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19projects in the council area
3awaiting a decision
14approved, not running
6%of decisions refused

How Enfield decides

ApplicationsEnfieldUK
Decided applications (solar, wind, battery)1610,236
Refused1 (6%)19%
Solar refused1 of 1612%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Projects in Enfield

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Iceland, Solar Wayrooftop solarrooftop solar2.6approved, not builtupdated Feb 2024Oct 2023granted Jan 2024Feb 2024
Smaller schemes under 1 MW, mostly rooftop solar (18)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Johnson Matthey, Jeffreys Roadrooftop solarrooftop solar0.7application submittedMay 2026——
Sainsburys Supermarketsrooftop solarrooftop solar0.7approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025
The Arenarooftop solarrooftop solar0.5approved, not builtupdated Aug 2024Jun 2024granted Aug 2024Aug 2024
The Arenarooftop solarrooftop solar0.5approved, not builtupdated Aug 2024Jun 2024granted Aug 2024Aug 2024
Chalkmill Driverooftop solarrooftop solar0.5application submittedMay 2026——
Solar Panels at 7 Solar Wayrooftop solarrooftop solar0.4approved, not builtupdated May 2024Oct 2023granted May 2024May 2024
Edmonton County School, Great Cambridge Roadrooftop solarrooftop solar0.3approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024
Eley Roadrooftop solarrooftop solar0.3approved, not builtupdated Apr 2022Apr 2022granted Jun 2022Apr 2022
Workstown Industrial Estate, Princes Roadrooftop solarrooftop solar0.3approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023
Southbury Roadrooftop solarrooftop solar0.3refusedupdated Oct 2024Aug 2024refused Oct 2024Oct 2024
Delta Park Industrial Estate, Millmarsh Lanerooftop solarrooftop solar0.3approved, not builtupdated Jul 2023Jun 2023granted Jul 2023Jul 2023
Edmonton lower schoolrooftop solarrooftop solar0.2approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024
Southbury Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2024granted Nov 2024Jan 2025
Lockfield Avenue Solarrooftop solarrooftop solar0.2under constructionupdated Apr 2021Oct 2020granted Dec 2020Apr 2021
Enfield County School For Girls, Holly Walkrooftop solarrooftop solar0.2application submittedMay 2026——
Sainsburys Supermarkets, Green Lanesrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Feb 2025granted Apr 2025Mar 2025
Advent Wayrooftop solarrooftop solar0.2operationalupdated Jan 2022Sep 2021granted Nov 2021Jan 2022
Heron Hall Academyrooftop solarrooftop solar0.1approved, not built may be out of dateupdated Mar 2022Mar 2022granted Jun 2022Mar 2022

Postcode districts in Enfield

DistrictProjects within 10 kmPendingApprovedOperational
EN1375272
EN2385264
EN3385282
N9445333
N13445323
N14475345
N18516383
N21385282

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Enfield by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.