Renewable energy projects in Hastings
5 solar, wind or battery projects of 150 kW or more are located in Hastings (REPD, July 2026 extract): 1 pending, 3 approved but not running, 0 operational and 0 refused.
5projects in the council area
1awaiting a decision
3approved, not running
0operational
How Hastings decides
Hastings has 4 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.
Projects in Hastings
Projects of 1 MW and more (1)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated |
|---|---|---|---|---|---|---|
| Queensway Southwind turbine | wind turbine | 2 | permission expiredupdated Dec 2017 | Jan 2009 | granted Jul 2009 | Dec 2017 |
Smaller schemes under 1 MW, mostly rooftop solar (4)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated |
|---|---|---|---|---|---|---|
| Combe Haven Holiday Park, Harley Shute Roadrooftop solar | rooftop solar | 0.5 | application submitted may be out of dateupdated Jan 2023 | Dec 2022 | — | Jan 2023 |
| Combe Haven Holiday Park, Harley Shute Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2023 | Feb 2023 | granted Mar 2023 | Mar 2023 |
| Morrisons, Queens Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2022 | Sep 2022 | granted Nov 2022 | Nov 2022 |
| Castleham Roadbattery storage | battery storage | 0.2 | approved, not builtupdated Dec 2024 | Oct 2024 | granted Dec 2024 | Dec 2024 |
Postcode districts in Hastings
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Hastings by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.