Energy Projects Near You

Renewable energy projects in Waverley

11 solar, wind or battery projects of 150 kW or more are located in Waverley (REPD, July 2026 extract): 3 pending, 6 approved but not running, 1 operational and 1 refused.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects in the council area
3awaiting a decision
6approved, not running
1operational

How Waverley decides

Waverley has 8 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Projects in Waverley

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Guildford Road Battery Storage Facilitybattery storagebattery storage14application submitted may be out of dateupdated Mar 2023Nov 2020—Mar 2023
Dunsfold Park Solar Farmsolar farmsolar farm2operationalupdated Mar 2013Nov 2010granted Mar 2011Mar 2013
Tuesley Farm, Tuesley Lanesolar farmsolar farm1approved, not builtupdated Apr 2025Jul 2023granted Nov 2023Apr 2025
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Sainsburys, Woolsack Wayrooftop solarrooftop solar0.6approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024
University For The Creative Arts, Falkner Roadrooftop solarrooftop solar0.6approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023
Brightwells Roadrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Jul 2022Jul 2022granted Nov 2022Jul 2022
David Lloyd Leisure Club, Wilkinson Wayrooftop solarrooftop solar0.3approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023
Kinetrol Manufacturing,Farnham Trading Estaterooftop solarrooftop solar0.2application submitted may be out of dateupdated Oct 2022Oct 2022—Oct 2022
Weybourne Roadbattery storagebattery storage0.2refusedupdated Jan 2025Aug 2024refused Nov 2024Jan 2025
Tilford Road, Nr Tower Road - Micro Energy Storage Facilitybattery storagebattery storage0.2application submittedupdated Sep 2024Aug 2024—Sep 2024
University For The Creative Arts, Falkner Road - ASHP & Battery Storagebattery storagebattery storage—approved, not built may be out of dateupdated May 2024Nov 2023granted Mar 2024May 2024

Postcode districts in Waverley

DistrictProjects within 10 kmPendingApprovedOperational
GU513481
GU66212
GU713481
GU86231
GU9231154
GU10223132
GU264120
GU272110

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Waverley by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.