Energy Projects Near You

Solar, wind and battery projects near Clitheroe (BB7)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BB7 (Ribble Valley): 1 is waiting for a planning decision, 4 approved but not yet running, 1 operational. The largest live scheme is Time Technology Park, Blackburn Road (1 MW rooftop solar, approved on 23 April 2024, not yet built), 8.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
1awaiting a decision
4approved, not running
1operational

Projects within 10 km of BB7

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Calder Works, Burnley Roadbattery storagebattery storage70application withdrawnupdated Oct 2024Jul 2024—Oct 2024Ribble Valley8.8
Padihambattery storagebattery storage99.9refusedupdated Feb 2025May 2024refused Dec 2024Feb 2025Burnley8.9
Altham Business Parkrooftop solarrooftop solar1.2operationalupdated Mar 2022Sep 2021granted Dec 2022Mar 2022Hyndburn9.4
Little Snodworth Solar Farmsolar farmsolar farm5refused on appealupdated Feb 2017Jul 2015refused Oct 2015Feb 2017Ribble Valley9.6
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Total Food Services, North Roadrooftop solarrooftop solar0.2under constructionupdated Feb 2023Nov 2022refused Jan 2023Feb 2023Ribble Valley3.3
Stonyhurst College, Avenue Roadrooftop solarrooftop solar—approved, not builtupdated Jun 2026Oct 2025granted Apr 2026Jun 2026Ribble Valley6.1
Time Technology Park, Blackburn Roadrooftop solarrooftop solar1approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024Ribble Valley8.8
Burnley Roadbattery storagebattery storage—permission expiredupdated Apr 2020Feb 2018granted Apr 2021Apr 2020Ribble Valley8.8
Newhouse Roadrooftop solarrooftop solar0.4application submitted may be out of dateupdated Apr 2022Feb 2021—Apr 2022Hyndburn9.3
Althamrooftop solarrooftop solar0.1approved, not builtupdated Apr 2022Feb 2021granted Jan 2022Apr 2022Hyndburn9.3

Distance from the average position of the BB7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm100010
Rooftop solar614101.8
Battery storage300010

MW in pipeline: pending, approved and under-construction capacity.

How Ribble Valley decides solar, wind and battery applications

Ribble Valley has 6 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in Ribble Valley

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BB7, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.