Energy Projects Near You

Solar, wind and battery projects near London (SW17)

48 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SW17 (Wandsworth): 8 are waiting for a planning decision, 35 approved but not yet running. The largest live scheme is Pegasus House, Sackville Street (2.3 MW rooftop solar, approved on 13 December 2021, not yet built; REPD status may be out of date), 8.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48projects within 10 km
8awaiting a decision
35approved, not running
0operational

Projects within 10 km of SW17

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Willow Lane Wind Turbineswind farmwind farm11abandonedupdated May 2014Jun 2004granted Aug 2004May 2014Merton4.3
Selhurst Traincare Depot, Selhurst Roadrooftop solarrooftop solar1approved, not builtupdated Mar 2026Oct 2025granted Nov 2025Mar 2026Croydon7.1
Pegasus House, Sackville Streetrooftop solarrooftop solar2.3approved, not built may be out of dateupdated Dec 2021Nov 2021granted Dec 2021Dec 2021Westminster8.9
Westfield London Shopping Centre, Ariel Wayrooftop solarrooftop solar1application submitted may be out of dateupdated Jul 2023Jun 2023—Jul 2023Hammersmith and Fulham9.4
Smaller schemes under 1 MW, mostly rooftop solar (44)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Springfield University Hospital, Lapidge Driverooftop solarrooftop solar—refusedupdated Apr 2026Dec 2025refused Feb 2026Apr 2026Wandsworth0.7
Grosvenor Wing, St Georges Hospitalrooftop solarrooftop solar—approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Wandsworth0.9
Springfield University Hospitalrooftop solarrooftop solar—approved, not builtupdated Jun 2026Nov 2025granted May 2026Jun 2026Wandsworth0.9
Sainsburys Superstore, Merton High Streetrooftop solarrooftop solar1approved, not builtupdated Sep 2024Aug 2024granted Sep 2024Sep 2024Merton2.1
JJ Foodservice, South Wimbledonrooftop solarrooftop solar0.3application submittedupdated Nov 2024Sep 2024—Nov 2024Merton2.4
Streatham Ice & Leisure, Streatham High Road Solar Panels & ASHProoftop solarrooftop solar0.3approved, not builtupdated Mar 2024Nov 2023granted Mar 2024Mar 2024Lambeth2.5
Morden Road, South Wimbledonrooftop solarrooftop solar0.1approved, not builtupdated Sep 2024Aug 2024granted Aug 2024Sep 2024Merton2.9
45 Clapham Campus South Side - 525 Flats & Education Facilityrooftop solarrooftop solar0.2application submitted may be out of dateupdated Apr 2023Oct 2022—Apr 2023Lambeth3.5
Knights Hill Solar PV equipmentrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Aug 2023granted Sep 2023Sep 2023Lambeth4.2
Harbour club, Watermeadow Lanerooftop solarrooftop solar0.4application withdrawnupdated Jul 2024Nov 2023—Jul 2024Hammersmith and Fulham4.5
David Lloyd Club, Bushey Roadrooftop solarrooftop solar0.8approved, not builtupdated Oct 2023Aug 2023granted Sep 2023Oct 2023Merton4.5
Battersea Studiosrooftop solarrooftop solar0.4approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Wandsworth4.8
Dulwich College, College Roadrooftop solarrooftop solar0.7approved, not builtupdated Feb 2025Jun 2024granted Dec 2024Feb 2025Southwark5.7
Chelsea And Westminster Hospital, Fulham Road - Photovoltaic Panelsrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026Kensington and Chelsea6.0
Wyvern Estate, Beverley Wayrooftop solarrooftop solar0.2approved, not builtupdated Dec 2022Sep 2022granted Oct 2022Dec 2022Merton6.4
Dolphin Squarerooftop solarrooftop solar—under constructionupdated May 2022Apr 2022granted Dec 2022May 2022Westminster6.5
Fulham Pools, Lillie Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2024Jan 2024granted Apr 2024May 2024Hammersmith and Fulham6.6
Kimpton Park Wayrooftop solarrooftop solar0.2application submitted may be out of dateupdated Sep 2023Aug 2023—Sep 2023Sutton6.7
William Booth Training College, Champion Parkrooftop solarrooftop solar—approved, not built may be out of dateupdated Jul 2023Feb 2023granted Aug 2023Jul 2023Southwark6.7
William Booth Training College, Champion Parkrooftop solarrooftop solar—application submitted may be out of dateupdated Jul 2023Jul 2023—Jul 2023Southwark6.7
St Anthonys Hospital, London Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024Sutton6.9
Sainsburys Supermarket, Trafalgar Wayrooftop solarrooftop solar0.6approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024Croydon7.0
The Queens Club, Palliser Roadrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Jun 2023Feb 2023granted May 2023Jun 2023Hammersmith and Fulham7.0
Westcroft Leisure Centre, Westcroft Roadrooftop solarrooftop solar0.3approved, not builtupdated Nov 2024Sep 2024granted Oct 2024Nov 2024Sutton7.1
Consession Queen Mother Sports Centrerooftop solarrooftop solar—application submitted may be out of dateupdated Oct 2021Oct 2021—Oct 2021Westminster7.2
Imperial College Health CentreSolar Panelsrooftop solarrooftop solar—application withdrawnupdated Apr 2021Feb 2021—Apr 2021Westminster7.5
Peckham Pulse Leisure Centre, Melon Roadrooftop solarrooftop solar0.2approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025Southwark8.1
Walworth Academy, Shorncliffe Roadrooftop solarrooftop solar0.3approved, not builtupdated Feb 2024Dec 2023granted Jan 2024Feb 2024Southwark8.7
Croydon Roadrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Bromley9.0
Trinity School Of John Whitgift, Shirley Roadrooftop solarrooftop solar—approved, not builtupdated Apr 2023Feb 2023granted Apr 2023Apr 2023Croydon9.0
Whitgift School, Nottingham Roadrooftop solarrooftop solar0.4application submitted may be out of dateupdated Sep 2022Aug 2022—Sep 2022Croydon9.1
The Spa, Beckenham Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2023Feb 2023granted Apr 2023May 2023Bromley9.2
Westfield London Shopping Centre, Ariel Wayrooftop solarrooftop solar0.3application submittedupdated Feb 2026Jan 2026—Feb 2026Hammersmith and Fulham9.4
David Lloyd Leisure Centre, Ewell Roadrooftop solarrooftop solar0.3approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Epsom and Ewell9.4
City Of London Academyrooftop solarrooftop solar0.2approved, not built may be out of dateupdated May 2022Feb 2022granted May 2022May 2022Southwark9.5
Devonhurst Placerooftop solarrooftop solar—approved, not built may be out of dateupdated Apr 2022Mar 2022granted May 2022Apr 2022Hounslow9.5
Bush Houserooftop solarrooftop solar—approved, not built may be out of dateupdated Jun 2021Apr 2021granted May 2021Jun 2021Westminster9.6
Richard Doll Building, Cotswold Roadrooftop solarrooftop solar0.5approved, not builtupdated Feb 2024Dec 2023granted Jan 2024Feb 2024Sutton9.7
Sainsburys Supermarkets, Essex Placerooftop solarrooftop solar0.3approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025Hounslow9.8
David Lloyd Leisure, Stanhope Groverooftop solarrooftop solar0.5approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023Bromley9.8
Kensington Leisure Centre, Silchester Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Mar 2023Oct 2022granted Feb 2023Mar 2023Kensington and Chelsea9.9
Sedgehill Academy, Sedgehill Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2026Sep 2025granted Nov 2025Jan 2026Lewisham9.9
Charrington Bowl, Kingston Roadrooftop solarrooftop solar0.3refusedupdated Nov 2022Sep 2022refused Oct 2022Nov 2022Kingston upon Thames9.9
The Bermondsey Projectrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Oct 2017granted Jun 2020Oct 2023Southwark9.9

Distance from the average position of the SW17 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar478350215.1
Wind farm100000

MW in pipeline: pending, approved and under-construction capacity.

How Wandsworth decides solar, wind and battery applications

Wandsworth has 5 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in Wandsworth

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SW17, 13 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.