Energy Projects Near You

Barnard Castle Solar Farm & Battery Storage System (16 MW)

Barnard Castle Solar Farm & Battery Storage System is a 16 MW solar farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 June 2025, not yet built; the record was last updated on 21 September 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16 MWsolar farm
approved, not builtstatus in REPD
21 September 2023record last updated
County Durhamcouncil area

Planning timeline

DateStage
21 August 2023Application submitted
10 June 2025Planning permission granted
10 June 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
16 MW
Status (REPD)
approved, not built
Record last updated
21 September 2023
Operator or applicant
Farm Energy Company
Planning authority
County Durham
Planning application reference
DM/23/02510/FPA
Site area
27.2 ha
Address (REPD)
Barnard Castle Solar Farm, A688 Marwood, Barnard Castle
Council area (by location)
County Durham
Time to decision
94 weeks
Name in REPD
Barnard Castle - Solar Farm & Battery Storage System
REPD reference
14839

The scheme also includes 4 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5512, -1.9056).