Blacksmiths Lane, Middlewood Green Solar Farm (30 MW)

Blacksmiths Lane, Middlewood Green Solar Farm is a 30 MW solar farm project in Mid Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 8 August 2025, not yet built; the record was last updated on 20 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
approved, not builtstatus in REPD
20 February 2026record last updated
Mid Suffolkcouncil area

Planning timeline

DateStage
11 October 2023Application submitted
8 August 2025Planning permission granted
8 August 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
Low Carbon Limited
Planning authority
Mid Suffolk
Planning application reference
DC/23/04644
Site area
36.3 ha
Address (REPD)
West Of Blacksmiths Lane Middlewood Green Earl Stonham
Council area (by location)
Mid Suffolk
Time to decision
95 weeks
Contracts for Difference
AR7a
Name in REPD
Blacksmiths Lane, Middlewood Green - Solar Farm
REPD reference
13530

Who decides

ApplicationsMid SuffolkUK
Decided applications (solar, wind, battery)3310,236
Refused5 (15%)19%
Solar refused3 of 1912%
Onshore wind refused1 of 245%
Battery storage refused1 of 1216%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2081, 1.0664).