Energy Projects Near You

Bolfornought Farm (49.9 MW battery storage)

Bolfornought Farm is a 49.9 MW battery storage project in Stirling, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 16 July 2021; the record was last updated on 16 July 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
application withdrawnstatus in REPD
16 July 2021record last updated
Scotlandcouncil area

Planning timeline

DateStage
14 April 2021Application submitted
16 July 2021Application withdrawn
28 January 2022Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
application withdrawn
Record last updated
16 July 2021
Operator or applicant
Intelligent Land Investments
Planning authority
Stirling
Planning application reference
21/00293/FUL
Address (REPD)
Land 650m SW Of Bolfornought F, Stirling, Central
Council area (by location)
not known
Time to decision
41 weeks
REPD reference
8072

Who decides

ApplicationsStirlingUK
Decided applications (solar, wind, battery)2310,236
Refused7 (30%)19%
Solar refused0 of 712%
Onshore wind refused6 of 1145%
Battery storage refused1 of 516%
Median time from submission to decision30.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bolfornought Farm Battery Storage Facilitybattery storage49.9application submitted<0.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3594, 2.3127).