California Wind Farm (21 MW)

California Wind Farm is a 21 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 19 July 2016; the record was last updated on 3 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21 MWwind farm
refused on appealstatus in REPD
3 August 2016record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
20 February 2015Application submitted
28 January 2016Appeal lodged
19 July 2016Refused by the planning authority
19 July 2016Appeal refused

Project details

Technology
wind farm
Capacity
21 MW
Status (REPD)
refused on appeal
Record last updated
3 August 2016
Operator or applicant
Ecotricity
Planning authority
Dumfries and Galloway
Planning application reference
15/P/2/0053
Appeal reference
PPA-170-2107
Turbines
7
Turbine height
110 m
Address (REPD)
Land north of the A75, Between Gatehouse of Feet and, Creetown, Near Carsluith
Council area (by location)
Dumfries and Galloway
Time to decision
74 weeks
REPD reference
4477

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8664, -4.3241).