Energy Projects Near You

East Lenham Solar Farm (6.6 MW)

East Lenham Solar Farm is a 6.6 MW solar farm project in Maidstone, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2014; the record was last updated on 29 September 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.6 MWsolar farm
operationalstatus in REPD
29 September 2015record last updated
Maidstonecouncil area

Planning timeline

DateStage
20 January 2012Application submitted
1 November 2012Planning permission granted
1 February 2014Construction started
30 March 2014Operational

Project details

Technology
solar farm
Capacity
6.6 MW
Status (REPD)
operational
Record last updated
29 September 2015
Operator or applicant
Laurence Associates
Planning authority
Maidstone
Planning application reference
12/0013
Site area
14.6 ha
Address (REPD)
East Lenham Farm, East Lenham Road, Lenham, Maidstone, Kent,
Council area (by location)
Maidstone
Time to decision
41 weeks
REPD reference
1816

Who decides

ApplicationsMaidstoneUK
Decided applications (solar, wind, battery)2110,236
Refused6 (29%)19%
Solar refused5 of 2012%
Battery storage refused1 of 116%
Median time from submission to decision8.1 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land South of Dowle Streetsolar9refused on appeal8.7
Pitstock Farmsolar farm41approved, not built9.3
Oaklands Farmsolar farm6.9operational9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2274, 0.7119).