Easter Parkhead Farm (19.9 MW battery storage)

Easter Parkhead Farm is a 19.9 MW battery storage project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 1 October 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19.9 MWbattery storage
abandonedstatus in REPD
1 October 2019record last updated
Scotlandcouncil area

Planning timeline

DateStage
23 May 2018Application submitted
9 October 2021Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
19.9 MW
Status (REPD)
abandoned
Record last updated
1 October 2019
Operator or applicant
Farmcare Trading
Planning authority
Perth and Kinross
Planning application reference
18/00687/FLL
Address (REPD)
Land 100m N/E of, 3 Parkhead Road, Parkhead Farm Cottage, Blairgowrie, Tayside
Council area (by location)
not known
REPD reference
7059

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6838, 3.0936).