Epwell Grounds Farm solar park (7 MW)

Epwell Grounds Farm solar park is a 7 MW solar farm project in Cherwell, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 10 December 2014; the record was last updated on 19 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
operationalstatus in REPD
19 March 2015record last updated
Cherwellcouncil area

Planning timeline

DateStage
21 October 2013Application submitted
13 January 2014Planning permission granted
13 October 2014Construction started
10 December 2014Operational

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
operational
Record last updated
19 March 2015
Operator or applicant
Private Developer
Planning authority
Cherwell
Planning application reference
13/01600/F
Site area
15.1 ha
Address (REPD)
Epwell Grounds Farm, Shutford Road, Epwell, Banbury
Council area (by location)
Cherwell
Time to decision
12 weeks
REPD reference
1899

Who decides

ApplicationsCherwellUK
Decided applications (solar, wind, battery)4410,236
Refused6 (14%)19%
Solar refused3 of 3712%
Onshore wind refused1 of 145%
Battery storage refused2 of 616%
Median time from submission to decision10.5 weeks17.0 weeks
Appeals lodged / allowed2 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hanwell Estate, Main Street Solar Farmsolar farm40application submitted7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0665, -1.4658).