Fawsley Estate, Fawsley Solar Arrays (12 MW)

Fawsley Estate, Fawsley Solar Arrays is a 12 MW solar farm project in West Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 January 2024, not yet built; the record was last updated on 19 February 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWsolar farm
approved, not builtstatus in REPD
19 February 2024record last updated
West Northamptonshirecouncil area

Planning timeline

DateStage
4 November 2022Application submitted
24 January 2024Planning permission granted

Project details

Technology
solar farm
Capacity
12 MW
Status (REPD)
approved, not built
Record last updated
19 February 2024
Operator or applicant
Elgin Energy EsCo
Planning authority
West Northamptonshire
Planning application reference
WND/2022/0901
Site area
24.2 ha
Address (REPD)
Fawsley Estate, Fawsley
Council area (by location)
West Northamptonshire
Time to decision
64 weeks
Name in REPD
Fawsley Estate, Fawsley - Solar Arrays
REPD reference
12700

Who decides

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Newnham Grange Farmbattery storage15application submitted6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2065, -1.181).