Energy Projects Near You

Gedney Marsh (12 MW wind farm)

Gedney Marsh is a 12 MW wind farm project in South Holland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 July 2008; the record was last updated on 6 May 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
operationalstatus in REPD
6 May 2009record last updated
South Hollandcouncil area

Planning timeline

DateStage
14 January 2003Application submitted
27 September 2003Planning permission granted
1 May 2006Construction started
15 July 2008Operational

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
6 May 2009
Operator or applicant
Wind Prospect
Planning authority
South Holland
Planning application reference
H06/0035/03
Turbines
6
Address (REPD)
Gedney Marsh Gedney Drove End Lincolnshire
Council area (by location)
South Holland
Time to decision
37 weeks
REPD reference
3133

Who decides

ApplicationsSouth HollandUK
Decided applications (solar, wind, battery)4410,236
Refused11 (25%)19%
Solar refused7 of 2612%
Onshore wind refused2 of 345%
Battery storage refused2 of 1516%
Median time from submission to decision13.8 weeks17.0 weeks
Appeals lodged / allowed5 / 6—

UK: all UK planning authorities. Counted under these REPD planning authority names: Lincolnshire, South Holland.

Other large projects within 10 km

ProjectTypeMWStatuskm
Holbeach Marsh Wind Farm,wind farm16abandoned1.7
Caudwell Farm, Hollbeachsolar farm49.9approved, not built2.1
Roman Bank, Middle Marsh Solar Farmsolar farm48refused5.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.8362, 0.1068).