Gedney Marsh (12 MW wind farm)
Gedney Marsh is a 12 MW wind farm project in South Holland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 July 2008; the record was last updated on 6 May 2009.
12 MWwind farm
operationalstatus in REPD
6 May 2009record last updated
South Hollandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 14 January 2003 | Application submitted |
| 27 September 2003 | Planning permission granted |
| 1 May 2006 | Construction started |
| 15 July 2008 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 12 MW
- Status (REPD)
- operational
- Record last updated
- 6 May 2009
- Operator or applicant
- Wind Prospect
- Planning authority
- South Holland
- Planning application reference
- H06/0035/03
- Turbines
- 6
- Address (REPD)
- Gedney Marsh Gedney Drove End Lincolnshire
- Council area (by location)
- South Holland
- Time to decision
- 37 weeks
- REPD reference
- 3133
Who decides
| Applications | South Holland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 44 | 10,236 |
| Refused | 11 (25%) | 19% |
| Solar refused | 7 of 26 | 12% |
| Onshore wind refused | 2 of 3 | 45% |
| Battery storage refused | 2 of 15 | 16% |
| Median time from submission to decision | 13.8 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 6 | — |
UK: all UK planning authorities. Counted under these REPD planning authority names: Lincolnshire, South Holland.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Holbeach Marsh Wind Farm, | wind farm | 16 | abandoned | 1.7 |
| Caudwell Farm, Hollbeach | solar farm | 49.9 | approved, not built | 2.1 |
| Roman Bank, Middle Marsh Solar Farm | solar farm | 48 | refused | 5.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.8362, 0.1068).