Glengolly Farmhouse- Battery Energy Storage (49.9 MW)

Glengolly Farmhouse- Battery Energy Storage is a 49.9 MW battery storage project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 September 2025, not yet built; the record was last updated on 4 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
4 November 2025record last updated
Scotlandcouncil area

Planning timeline

DateStage
6 March 2024Application submitted
1 April 2025Refused by the planning authority
30 September 2025Appeal allowed
30 September 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
4 November 2025
Operator or applicant
Ecocel Energy Storage Limited
Planning authority
Highland
Planning application reference
24/00561/FUL
Address (REPD)
Land 500M East Of Glengolly Farmhouse Thurso
Council area (by location)
not known
Time to decision
56 weeks
REPD reference
15088

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4001, 6.328).