Glenvernoch Wind Farm (86 MW)

Glenvernoch Wind Farm is an 86 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 12 November 2024, no decision recorded; the record was last updated on 16 January 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

86 MWwind farm
application submittedstatus in REPD
16 January 2026record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
12 November 2024Application submitted

Project details

Technology
wind farm
Capacity
86 MW
Status (REPD)
application submitted
Record last updated
16 January 2026
Operator or applicant
Energiekontor (UK) Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004892
Turbines
13
Turbine height
200 m
Address (REPD)
Glentrool, Newton Stewart
Council area (by location)
Dumfries and Galloway
REPD reference
14761

The scheme also includes battery storage, recorded separately in REPD (application submitted).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Hill of Ochiltreewind farm23refused3.3
Blair Hill Wind Farmwind farm145application submitted6.1
Challoch, Barnkirk Road Solar Array & Battery Energy Storagesolar farm20application submitted6.7
Challoch, Barnkirk Road Solar Array & Battery Energy Storagebattery storage6application submitted6.7
Balunton Wind Farmwind farm27application withdrawn7.4
Shennanton Wind Farmwind farm30refused on appeal8.8
Shennanton Wind Farmwind farm30application submitted9.0
Corwar Wind Farmwind farm16.4refused on appeal9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0266, -4.579).