High Moor Wind Farm (14.7 MW)

High Moor Wind Farm is a 14.7 MW wind farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 12 November 1998; the record was last updated on 30 October 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.7 MWwind farm
refusedstatus in REPD
30 October 2011record last updated
County Durhamcouncil area

Planning timeline

DateStage
26 April 1996Application submitted
12 November 1998Refused by the planning authority

Project details

Technology
wind farm
Capacity
14.7 MW
Status (REPD)
refused
Record last updated
30 October 2011
Operator or applicant
National Windpower
Planning authority
County Durham
Planning application reference
not recorded
Address (REPD)
High Moor Barningham Durham
Council area (by location)
County Durham
Time to decision
133 weeks
REPD reference
2599

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.4629, -1.9352).