Energy Projects Near You

Hill Farm (5 MW solar farm)

Hill Farm is a 5 MW solar farm project in Cherwell, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2017; the record was last updated on 3 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
3 May 2017record last updated
Cherwellcouncil area

Planning timeline

DateStage
31 March 2015Application submitted
16 October 2015Planning permission granted
1 February 2017Construction started
1 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
3 May 2017
Operator or applicant
NESF (formerly Earthworm)
Planning authority
Cherwell
Planning application reference
15/00570/F
Address (REPD)
Hill Farm, Hill Farm Lane, Duns Tew, Bicester, Oxfordshire
Council area (by location)
Cherwell
Time to decision
28 weeks
REPD reference
5164

Who decides

ApplicationsCherwellUK
Decided applications (solar, wind, battery)4410,236
Refused6 (14%)19%
Solar refused3 of 3712%
Onshore wind refused1 of 145%
Battery storage refused2 of 616%
Median time from submission to decision10.5 weeks17.0 weeks
Appeals lodged / allowed2 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land North of Hill Farmsolar farm8.9approved, not built0.5
Fewcott Wind Farmwind farm9.2abandoned7.0
Station Road, Ardley Solar Farm & Battery Energy Storage Systemsolar farm10.5application submitted8.8
Wootton Balksolar7.5refused9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9621, -1.3333).