Energy Projects Near You

Hillhead of Auquhirie (6.9 MW wind farm)

Hillhead of Auquhirie is a 6.9 MW wind farm project in Grampian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 16 January 2013; the record was last updated on 25 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.9 MWwind farm
operationalstatus in REPD
25 March 2015record last updated
Scotlandcouncil area

Planning timeline

DateStage
4 November 2009Application submitted
10 January 2011Planning permission granted
1 September 2012Construction started
16 January 2013Operational

Project details

Technology
wind farm
Capacity
6.9 MW
Status (REPD)
operational
Record last updated
25 March 2015
Operator or applicant
Octopus Investements/Blue Energy (previously Auquhirie Land Company Ltd)
Planning authority
Aberdeenshire
Planning application reference
APP/2009/3567
Turbines
3
Address (REPD)
Hillhead of Auquhirie, Stonehaven
Council area (by location)
not known
Time to decision
62 weeks
REPD reference
3701

Earlier applications for this site

ApplicationMWSubmittedOutcome
Hillhead of Auquhirie APP/2006/177769 May 2006withdrawn 2 October 2008

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.9552, -3.1772).