Energy Projects Near You

Renewable energy projects in Brighton and Hove

5 solar, wind or battery projects of 150 kW or more are located in Brighton and Hove (REPD, July 2026 extract): 0 pending, 4 approved but not running, 1 operational and 0 refused.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects in the council area
0awaiting a decision
4approved, not running
1operational

How Brighton and Hove decides

Brighton and Hove has 5 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Projects in Brighton and Hove

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
ParkerSteel Shoreham Plantrooftop solarrooftop solar1.8operationalupdated Mar 2016Mar 2015granted Mar 2015Mar 2016
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Old Shoreham Roadrooftop solarrooftop solar0.6approved, not builtupdated May 2025Mar 2025granted May 2025May 2025
Hove Polyclinic, Nevill Avenuerooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025
Cemex Brighton Plant & Wharf, Wellington Roadbattery storagebattery storage—approved, not builtupdated Feb 2025Oct 2024granted Jan 2025Feb 2025
Cemex Brighton Plant & Wharf, Wellington Roadrooftop solarrooftop solar—approved, not builtupdated Feb 2025Oct 2024granted Jan 2025Feb 2025

Postcode districts in Brighton and Hove

DistrictProjects within 10 kmPendingApprovedOperational
BN16051
BN25041
BN38061
BN4114192

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Brighton and Hove by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.