Energy Projects Near You

Solar, wind and battery projects near Brighton (BN1)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BN1 (Brighton and Hove): 5 approved but not yet running, 1 operational. The largest live scheme is Old Shoreham Road (0.6 MW rooftop solar, approved on 1 May 2025, not yet built), 4.6 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Rampion 2 Offshore Wind Farm (Rampion extension) (1,200 MW, approved, not built), 22.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
0awaiting a decision
5approved, not running
1operational

Projects within 10 km of BN1

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
ParkerSteel Shoreham Plantrooftop solarrooftop solar1.8operationalupdated Mar 2016Mar 2015granted Mar 2015Mar 2016Brighton and Hove5.6
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hove Polyclinic, Nevill Avenuerooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Brighton and Hove3.5
Old Shoreham Roadrooftop solarrooftop solar0.6approved, not builtupdated May 2025Mar 2025granted May 2025May 2025Brighton and Hove4.6
Cemex Brighton Plant & Wharf, Wellington Roadbattery storagebattery storage—approved, not builtupdated Feb 2025Oct 2024granted Jan 2025Feb 2025Brighton and Hove4.7
Cemex Brighton Plant & Wharf, Wellington Roadrooftop solarrooftop solar—approved, not builtupdated Feb 2025Oct 2024granted Jan 2025Feb 2025Brighton and Hove4.7
Dunelmrooftop solarrooftop solar0.2approved, not builtupdated Jul 2025Apr 2025granted Jul 2025Jul 2025Adur8.9

Distance from the average position of the BN1 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar504100.9
Battery storage101000

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Rampion 2 Offshore Wind Farm (Rampion extension)1,200approved, not builtupdated May 202522.7
Rampion Offshore Wind Farm (Hastings Zone)400operationalupdated Dec 201922.7

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Brighton and Hove decides solar, wind and battery applications

Brighton and Hove has 5 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in Brighton and Hove

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.