Rampion 2 Offshore Wind Farm (Rampion extension) offshore wind farm

Rampion 2 Offshore Wind Farm (Rampion extension) is a 1,200 MW offshore wind farm with 90 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 April 2025, not yet built; the record was last updated on 6 May 2025. Its REPD grid reference is 20 km from the nearest postcode on land (BN2 5ZD, Brighton and Hove). As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010117).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1,200 MWoffshore wind farm
approved, not builtstatus in REPD
6 May 2025record last updated
20 km from land (Brighton and Hove)REPD location

Consent timeline

DateStage
10 August 2023Application submitted
4 April 2025Development consent granted (Secretary of State)
4 April 2032Permission due to expire (unless work starts)

Project details

Technology
offshore wind farm
Capacity
1,200 MW
Turbines
90
Turbine height
325 m
Status (REPD)
approved, not built
Record last updated
6 May 2025
Operator or applicant
RWE Renewables UK Limited
Consenting authority (REPD)
The Planning Inspectorate - National Infrastructure
Application reference
EN010117
Nearest postcode on land
BN2 5ZD (Brighton and Hove), 19.7 km from the REPD grid reference
Time to decision
86 weeks
Name in REPD
Rampion Wind Farm (Extension), (Rampion 2)
REPD reference
7698

Official project record at the Planning Inspectorate

Who decides

As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010117). All Energy Secretary decisions on solar and wind farms.

Postcode districts within 40 km

Districtkm
Brighton (BN2)21.3
Peacehaven (BN10)21.6
Hove (BN3)21.7
Brighton (BN42)22.3
Brighton (BN41)22.5
Shoreham-by-Sea (BN43)22.6
Brighton (BN1)22.7
Lancing (BN15)23.5
Newhaven (BN9)23.7
Worthing (BN11)23.8
Seaford (BN25)25.4
Worthing (BN14)25.8

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Rampion Offshore Wind Farm (Hastings Zone)400operational<0.1

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (50.64, -0.18).