Energy Projects Near You

Rampion Offshore Wind Farm (Hastings Zone) offshore wind farm

Rampion Offshore Wind Farm (Hastings Zone) is a 400 MW offshore wind farm with 116 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 November 2017; the record was last updated on 6 December 2019. Its REPD grid reference is 20 km from the nearest postcode on land (BN2 5ZD, Brighton and Hove). As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (EN010032).

How it works ↓

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWoffshore wind farm
operationalstatus in REPD
6 December 2019record last updated
20 km from land (Brighton and Hove)REPD location

Consent timeline

DateStage
25 March 2013Application submitted
16 July 2014Development consent granted (Secretary of State)
25 January 2016Construction started
26 November 2017Operational

Project details

Technology
offshore wind farm
Capacity
400 MW
Turbines
116
Turbine capacity
3.5 MW
Turbine height
140 m
Status (REPD)
operational
Record last updated
6 December 2019
Operator or applicant
E.ON UK
Consenting authority (REPD)
The Planning Inspectorate - National Infrastructure
Application reference
EN010032
Nearest postcode on land
BN2 5ZD (Brighton and Hove), 19.7 km from the REPD grid reference
Time to decision
68 weeks
REPD reference
2520

Official project record at the Planning Inspectorate

Who decides

As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (EN010032). All Energy Secretary decisions on solar and wind farms.

Postcode districts within 40 km

Districtkm
Brighton (BN2)21.3
Peacehaven (BN10)21.6
Hove (BN3)21.7
Brighton (BN42)22.3
Brighton (BN41)22.5
Shoreham-by-Sea (BN43)22.6
Brighton (BN1)22.7
Lancing (BN15)23.5
Newhaven (BN9)23.7
Worthing (BN11)23.8
Seaford (BN25)25.4
Worthing (BN14)25.8

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Rampion 2 Offshore Wind Farm (Rampion extension)1,200approved, not built<0.1

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (50.64, -0.18).

Rampion, listed in the REPD as Rampion Offshore Wind Farm (Hastings Zone), is 116 turbines of 3.5 MW each, 140 m tall, 400 MW in total, off Brighton and Hove. The applicant on record is E.ON UK. The roughly 20 km to the shore should be read as a straight line from a single reference point in the register to the postcode BN2 5ZD, not to the edge of the turbine field. The postcode districts BN2, BN10 and BN3 lie 21–22 km away, and there are 12 of them within 26 km.

How Rampion was approved

The application was submitted on 25 March 2013. After examination by the Planning Inspectorate (EN010032), the Energy Secretary granted the development consent order (DCO) for this nationally significant project on 16 July 2014, after 68 weeks; the median for offshore wind is 84.4. Construction began on 25 January 2016, and on 26 November 2017 the wind farm became operational: four and a half years from application.

Rampion 2

The follow-on project, Rampion 2 at 1,200 MW, is recorded separately at the same point in the register and, going by the extract for July 2026, is approved, not built. The record for the first Rampion has not been updated since 6 December 2019, so the register may well be lagging behind.