Energy Projects Near You

Solar, wind and battery projects near Solihull (B91)

45 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of B91 (Solihull): 8 are waiting for a planning decision, 33 approved but not yet running. The largest live scheme is Henwood Lane, Catherine De Barnes (98 MW battery storage, approved on 30 July 2025, not yet built), 3.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

45projects within 10 km
8awaiting a decision
33approved, not running
0operational

Projects within 10 km of B91

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Solar Panels at Woodhouse Farmsolar farmsolar farm49.9application submittedupdated Sep 2025Jul 2025—Sep 2025Solihull3.2
Castle Hills Solar Farmsolar farmsolar farm5application submittedupdated Sep 2025Jul 2025—Sep 2025Solihull3.2
Henwood Lane, Catherine De Barnesbattery storagebattery storage98approved, not builtupdated Aug 2025Sep 2023granted Jul 2025Aug 2025Solihull3.2
NEC, Birminghamrooftop solarrooftop solar3.9abandonedupdated Mar 2018Aug 2015granted Oct 2015Mar 2018Solihull6.0
Holly Lane Energy Park Solar Farm & Battery Storagesolar farmsolar farm25approved, not builtupdated Feb 2026Sep 2023granted Jan 2025Feb 2026Solihull6.6
Ryton End, Barstonbattery storagebattery storage15refusedupdated May 2024Sep 2022refused May 2024May 2024Solihull6.8
Fordhouse Lanebattery storagebattery storage20approved, not builtupdated Oct 2024Jan 2023granted Aug 2023Oct 2024Birmingham9.0
Birmingham And Solihull Rugby Club, Forshaw Heath Lanesolar farmsolar farm1.2application submittedupdated Mar 2025Feb 2025—Mar 2025Stratford-on-Avon9.2
Smaller schemes under 1 MW, mostly rooftop solar (37)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Paragon House, Homer Roadrooftop solarrooftop solar0.3approved, not builtupdated Jun 2026Apr 2026granted Jun 2026Jun 2026Solihull0.2
Solihull Hospital, Lode Lanerooftop solarrooftop solar0.3application submittedApr 2026——Solihull0.7
Tudor Grange, Solihull Dingle Lane PV Solar Panelsrooftop solarrooftop solar0.5approved, not builtupdated Nov 2023Oct 2023granted Nov 2023Nov 2023Solihull1.2
Tudor Grange Academy, Dingle Lanerooftop solarrooftop solar0.3approved, not builtupdated Apr 2024Feb 2024granted Apr 2024Apr 2024Solihull1.2
Solar Array at Unit 500rooftop solarrooftop solar—approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Solihull2.3
Farmfoods Limited, Highlands Roadrooftop solarrooftop solar0.5approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Solihull2.4
Langley Academy, Kineton Green Road, Oltonrooftop solarrooftop solar0.3approved, not builtupdated Aug 2025Jun 2025granted Aug 2025Aug 2025Solihull2.5
Jaguar Land Rover, Lode Lane – Battery Storage Unitbattery storagebattery storage—approved, not built may be out of dateupdated Jul 2023Apr 2023granted Jul 2023Jul 2023Solihull2.5
Cranmore Boulevard, Shirley Solar Photo Voltaic Systemrooftop solarrooftop solar0.3approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024Solihull2.7
Copt Heath Golf Club Solar Farmsolar farmsolar farm0.3approved, not builtupdated Feb 2025Jan 2024granted May 2024Feb 2025Solihull3.1
The Gate, International Drivesolar farmsolar farm0.8application submittedMay 2026——Solihull3.3
The Gate, International Drivebattery storagebattery storage—application submittedMay 2026——Solihull3.3
Eagle Two, Hatchford Wayrooftop solarrooftop solar0.3application withdrawnupdated Jan 2026Jan 2025—Jan 2026Birmingham4.4
Eagle 3, Hatchford Wayrooftop solarrooftop solar0.3application submittedupdated May 2026Mar 2026—May 2026Birmingham4.4
One Central Boulevard, Central Boulevardrooftop solarrooftop solar0.2approved, not builtupdated Oct 2022Aug 2022granted Sep 2022Oct 2022Solihull4.5
Hampton Manorsolar farmsolar farm0.3refusedupdated Jun 2020Sep 2019refused Apr 2020Jun 2020Solihull5.4
Birmingham Airport, Diamond Houserooftop solarrooftop solar1approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Solihull5.5
Parfetts Cash and Carry, Redfern Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2025Nov 2024granted Dec 2024Jan 2025Birmingham5.8
The Palletline Centre, Starley Way - Roof Mounted Solar PV arrayrooftop solarrooftop solar0.1approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Solihull6.1
Formans Road, Tyseleyrooftop solarrooftop solar0.3approved, not builtupdated May 2023Feb 2023granted Apr 2023May 2023Birmingham6.1
Cole Valley, Westwood Avenuerooftop solarrooftop solar0.8approved, not builtupdated Apr 2023Mar 2023granted Apr 2023Apr 2023Birmingham6.3
Greet Primary School, Percy Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024Birmingham6.7
Unit B, Progress Wayrooftop solarrooftop solar—approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024Solihull6.8
Progress Way, Marston Greenrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024Solihull6.8
Golden Hillock Road, Sparkbrookrooftop solarrooftop solar0.7approved, not builtupdated Feb 2024Dec 2023granted Feb 2024Feb 2024Birmingham7.4
Melbicks Garden Centre, Chester Roadrooftop solarrooftop solar0.4approved, not built may be out of dateupdated Nov 2022Sep 2022granted Nov 2022Nov 2022North Warwickshire7.6
Birmingham Heartlands Hospital - Roof Top Solar Farmrooftop solarrooftop solar0.6approved, not builtupdated Jul 2022Jun 2022granted Oct 2022Jul 2022Birmingham7.7
Bishop Wilson Ce Primary School, Craig Croftrooftop solarrooftop solar0.4approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026Solihull8.1
Vertik-Al,Yardley Brook Industrial Parkrooftop solarrooftop solar0.5approved, not builtupdated Jan 2023Nov 2022granted Dec 2022Jan 2023Birmingham8.2
Tudor Grange Academy, Kingshurst Cooks Lane - Photovoltaic Solar Panelsrooftop solarrooftop solar0.4approved, not builtupdated Dec 2023Sep 2023granted Nov 2023Dec 2023Solihull8.6
Poolhead Lane, Earlswoodrooftop solarrooftop solar0.3approved, not builtupdated Sep 2025Aug 2025granted Sep 2025Sep 2025Stratford-on-Avon8.7
Morrisons, Coventry Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2025Mar 2025granted Apr 2025May 2025Birmingham8.8
Eden Boys Leadership Academy, Alum Rock Roadrooftop solarrooftop solar—approved, not builtupdated Aug 2023May 2023granted Aug 2023Aug 2023Birmingham9.1
Birmingham And Solihull Rugby Club, Forshaw Heath Lanebattery storagebattery storage—application submittedupdated Mar 2025Feb 2025—Mar 2025Stratford-on-Avon9.2
Tesco Stores, Coleshill Roadrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Dec 2024granted Feb 2025Feb 2025Birmingham9.2
Selly Park Girls School, Selly Park Roadrooftop solarrooftop solar0.3approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026Birmingham9.6
Network Park Industrial Estate, Duddeston Mill Roadrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026Birmingham10.0

Distance from the average position of the B91 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm7420182.2
Rooftop solar322280010.6
Battery storage62301118

MW in pipeline: pending, approved and under-construction capacity.

How Solihull decides solar, wind and battery applications

ApplicationsSolihullUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused4 of 2212%
Battery storage refused4 of 816%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed4 / 4—

All projects in Solihull

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near B91, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.