Energy Projects Near You

Solar Panels at Woodhouse Farm (49.9 MW)

Solar Panels at Woodhouse Farm is a 49.9 MW solar farm project in Solihull, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 29 July 2025, no decision recorded; the record was last updated on 12 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
application submittedstatus in REPD
12 September 2025record last updated
Solihullcouncil area

Planning timeline

DateStage
29 July 2025Application submitted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
12 September 2025
Operator or applicant
Castle Hills Solar Farm Limited
Planning authority
Solihull
Planning application reference
PL/2025/01404/PPFL
Site area
104.0 ha
Address (REPD)
Woodhouse Farm, Catherine De Barnes Lane, Catherine De Barnes, Solihull
Council area (by location)
Solihull
Name in REPD
Castle Hills Solar Farm - Solar Panels
REPD reference
19475

Recorded together with Castle Hills Solar Farm (5 MW solar farm, application submitted).

Who decides

ApplicationsSolihullUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused4 of 2212%
Battery storage refused4 of 816%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed4 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Henwood Lane, Catherine De Barnesbattery storage98approved, not built2.1
Holly Lane Energy Park Solar Farm & Battery Storagesolar farm25approved, not built4.7
Ryton End, Barstonbattery storage15refused4.8
Hill House Farm, Coventry Roadbattery storage20application submitted8.2
Benton Green Lanebattery storage70application submitted8.9
Broad Lanesolar farm8.5refused on appeal9.2
Beechwood Farm, Hodgetts Lanebattery storage57approved, not built9.3
Beechwood Farm, Hodgetts Lanebattery storage57application submitted9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.429, -1.7439).