Beechwood Farm, Hodgetts Lane (57 MW battery storage, 2023 application)

Beechwood Farm, Hodgetts Lane is a 57 MW battery storage project in Solihull, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 9 January 2025, not yet built; the record was last updated on 20 January 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

57 MWbattery storage
approved, not builtstatus in REPD
20 January 2025record last updated
Solihullcouncil area

Planning timeline

DateStage
18 April 2023Application submitted
10 November 2023Refused by the planning authority
8 May 2024Appeal lodged
9 January 2025Planning permission granted
9 January 2025Appeal allowed
9 January 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
57 MW
Status (REPD)
approved, not built
Record last updated
20 January 2025
Operator or applicant
Enso Energy Limited
Planning authority
Solihull
Planning application reference
PL/2023/00839/PPFL
Appeal reference
AP/2024/00020/REF
Address (REPD)
Beechwood Farm Hodgetts Lane Berkswell
Council area (by location)
Solihull
Time to decision
90 weeks
Name in REPD
Beechwood Farm, Hodgetts Lane - Battery Storage
REPD reference
13297

Who decides

ApplicationsSolihullUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused4 of 2212%
Battery storage refused4 of 816%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed4 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Beechwood Farm, Hodgetts Lanebattery storage57application submitted<0.1
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage49.9application submitted0.4
Nailcote Farmsolar farm18refused0.6
Little Beanit Farm, Balsall Commonbattery storage200under construction0.6
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage49.9approved, not built0.9
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage49.9application submitted0.9
Benton Green Lanebattery storage70application submitted1.4
Tanners Lanebattery storage30approved, not built1.7
Burton Green Farmbattery storage100approved, not built2.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3914, -1.6217).