Energy Projects Near You

Little Beanit Farm, Balsall Common (200 MW battery storage)

Little Beanit Farm, Balsall Common is a 200 MW battery storage project in Solihull, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 September 2025; the record was last updated on 9 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

200 MWbattery storage
under constructionstatus in REPD
9 March 2026record last updated
Solihullcouncil area

Planning timeline

DateStage
28 October 2022Application submitted
31 August 2023Planning permission granted
1 September 2025Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
200 MW
Status (REPD)
under construction
Record last updated
9 March 2026
Operator or applicant
Penso Power (BW ESS)
Planning authority
Solihull
Planning application reference
PL/2022/02308/PPFL
Address (REPD)
Little Beanit Farm Waste Lane Balsall Common Solihull
Council area (by location)
Solihull
Time to decision
44 weeks
Name in REPD
Little Beanit Farm, Balsall Common - Battery Storage
REPD reference
11656

Who decides

ApplicationsSolihullUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused4 of 2212%
Battery storage refused4 of 816%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed4 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Beechwood Farm, Hodgetts Lanebattery storage57approved, not built0.6
Beechwood Farm, Hodgetts Lanebattery storage57application submitted0.6
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage49.9application submitted0.7
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage49.9application submitted1.0
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage49.9approved, not built1.0
Nailcote Farmsolar farm18refused1.1
Burton Green Farmbattery storage100approved, not built1.6
Benton Green Lanebattery storage70application submitted2.0
Tanners Lanebattery storage30approved, not built2.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3861, -1.6251).