Nailcote Farm (18 MW solar farm)

Nailcote Farm is an 18 MW solar farm project in Solihull, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 3 November 2014; the record was last updated on 9 February 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWsolar farm
refusedstatus in REPD
9 February 2015record last updated
Solihullcouncil area

Planning timeline

DateStage
9 July 2014Application submitted
3 November 2014Refused by the planning authority

Project details

Technology
solar farm
Capacity
18 MW
Status (REPD)
refused
Record last updated
9 February 2015
Operator or applicant
Green Energy UK Direct
Planning authority
Solihull
Planning application reference
2014/1212
Site area
19.0 ha
Address (REPD)
Nailcote Farm, Nailcote Lane, Berkswell, Coventry
Council area (by location)
Solihull
Time to decision
17 weeks
REPD reference
2250

Who decides

ApplicationsSolihullUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused4 of 2212%
Battery storage refused4 of 816%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed4 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage49.9application submitted0.4
Beechwood Farm, Hodgetts Lanebattery storage57application submitted0.6
Beechwood Farm, Hodgetts Lanebattery storage57approved, not built0.6
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage49.9approved, not built0.7
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage49.9application submitted0.7
Little Beanit Farm, Balsall Commonbattery storage200under construction1.1
Tanners Lanebattery storage30approved, not built1.2
Benton Green Lanebattery storage70application submitted1.3
Burton Green Farmbattery storage100approved, not built2.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3927, -1.6129).