Burton Green Farm (100 MW battery storage)

Burton Green Farm is a 100 MW battery storage project in Warwick, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 9 July 2025, not yet built; the record was last updated on 29 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
approved, not builtstatus in REPD
29 July 2025record last updated
Warwickcouncil area

Planning timeline

DateStage
27 September 2024Application submitted
9 July 2025Planning permission granted
9 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
approved, not built
Record last updated
29 July 2025
Operator or applicant
Conrad Energy (Developments) Limited
Planning authority
Solihull
Planning application reference
PL/2024/01948/PPFL
Address (REPD)
Burton Green Farm, Hob Lane, Kenilworth
Council area (by location)
Warwick
Time to decision
41 weeks
Name in REPD
Burton Green Farm - Battery Energy Storage
REPD reference
17274

Who decides

ApplicationsSolihullUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused4 of 2212%
Battery storage refused4 of 816%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed4 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage49.9approved, not built1.3
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage49.9application submitted1.3
Little Beanit Farm, Balsall Commonbattery storage200under construction1.6
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage49.9application submitted1.7
Beechwood Farm, Hodgetts Lanebattery storage57application submitted2.0
Beechwood Farm, Hodgetts Lanebattery storage57approved, not built2.0
Nailcote Farmsolar farm18refused2.0
Tanners Lanebattery storage30approved, not built3.1
Benton Green Lanebattery storage70application submitted3.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3749, -1.6105).