Energy Projects Near You

Solar, wind and battery projects near Coventry (CV1)

63 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CV1 (Coventry): 15 are waiting for a planning decision, 40 approved but not yet running, 1 operational. The largest live scheme is T Main Road, Ansty (200 MW battery storage, approved on 12 September 2024, not yet built), 7.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

63projects within 10 km
15awaiting a decision
40approved, not running
1operational

Projects within 10 km of CV1

Projects of 1 MW and more (33)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Torrington Avenue Battery Storage Facilitybattery storagebattery storage30approved, not builtupdated Apr 2024Jan 2024granted Apr 2024Apr 2024Coventry4.6
Central Boulevard, Prologis Parkrooftop solarrooftop solar1.6approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026Coventry5.2
Lentons Lane, Aldermans Greensolar farmsolar farm25refusedupdated May 2026Oct 2025refused Apr 2026May 2026Coventry5.3
Lentons Lanesolar farmsolar farm25approved, not builtupdated May 2026Oct 2025granted Jan 2026May 2026Coventry5.3
Coventry National Grid Substationbattery storagebattery storage49.9operationalupdated Jul 2025Jul 2020granted Jan 2021Jul 2025Coventry5.8
Mcdonnell Drive, Exhallbattery storagebattery storage30approved, not builtupdated Nov 2025Jun 2025granted Oct 2025Nov 2025Nuneaton and Bedworth5.8
Lentons Lane Solar Farmsolar farmsolar farm30refusedupdated Apr 2024May 2023refused Mar 2024Apr 2024Coventry5.9
Coventry National Grid Substation, Hawkesbury Hallbattery storagebattery storage98application submittedupdated Dec 2025Jul 2025—Dec 2025Coventry5.9
Tolldish Hall Farm, Parrotts Grovesolar farmsolar farm25under constructionupdated Sep 2025Oct 2022granted Aug 2023Sep 2025Rugby6.5
Tanners Lanebattery storagebattery storage30approved, not builtupdated Jul 2025Nov 2024granted Jun 2025Jul 2025Coventry6.7
Broad Lanesolar farmsolar farm8.5refused on appealupdated Mar 2017Sep 2015refused Feb 2016Mar 2017Coventry7.1
Nailcote Farmsolar farmsolar farm18refusedupdated Feb 2015Jul 2014refused Nov 2014Feb 2015Solihull7.5
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storagebattery storage49.9approved, not builtupdated Feb 2025Oct 2023granted Jan 2025Feb 2025Warwick7.5
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storagebattery storage49.9application submitted may be out of dateupdated Feb 2025Jul 2024—Feb 2025Warwick7.5
T Main Road, Anstybattery storagebattery storage200approved, not builtupdated Sep 2024Feb 2024granted Sep 2024Sep 2024Rugby7.5
Hollyhurst Farm, Mile Tree Lanesolar farmsolar farm25.6application submittedupdated Mar 2025Dec 2024—Mar 2025Nuneaton and Bedworth7.5
Newgate Coolliery Solar Farm & Battery Storagesolar farmsolar farm6application submitted may be out of dateupdated Jun 2024May 2024—Jun 2024Nuneaton and Bedworth7.6
Newgate Coolliery Solar Farm & Battery Storagebattery storagebattery storage5application submitted may be out of dateupdated Jun 2024May 2024—Jun 2024Nuneaton and Bedworth7.6
Corley Smorral Lane - Photovoltaic Solar Arrayssolar farmsolar farm16.5approved, not built may be out of dateupdated Nov 2021Nov 2021granted Jul 2022Nov 2021Nuneaton and Bedworth7.7
Benton Green Lanebattery storagebattery storage70application submittedupdated Jul 2025Jun 2025—Jul 2025Solihull7.7
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storagebattery storage49.9application submitted may be out of dateupdated Aug 2023Jul 2023—Aug 2023Solihull7.7
Burton Green Farmbattery storagebattery storage100approved, not builtupdated Jul 2025Sep 2024granted Jul 2025Jul 2025Warwick8.0
Beechwood Farm, Hodgetts Lanebattery storagebattery storage57approved, not builtupdated Jan 2025Apr 2023granted Jan 2025Jan 2025Solihull8.1
Beechwood Farm, Hodgetts Lanebattery storagebattery storage57application submitted may be out of dateupdated Jan 2025Jul 2024—Jan 2025Solihull8.1
Hill House Farm, Coventry Roadbattery storagebattery storage20application submittedupdated Jun 2025Apr 2025—Jun 2025Solihull8.1
Highwood Farmrooftop solarrooftop solar1.3permission expiredupdated Aug 2020Apr 2016granted Jun 2016Aug 2020Rugby8.4
Little Beanit Farm, Balsall Commonbattery storagebattery storage200under constructionupdated Mar 2026Oct 2022granted Aug 2023Mar 2026Solihull8.5
Vauls Farm, Astley Lane Solar Farmsolar farmsolar farm16approved, not built may be out of dateupdated Aug 2023Oct 2022granted Jul 2023Aug 2023North Warwickshire8.7
Holly Lane Energy Park Solar Farm & Battery Storagebattery storagebattery storage75approved, not builtupdated Feb 2026Sep 2023granted Jan 2025Feb 2026Solihull9.1
Park House Farm, Meriden Road Solar Farmsolar farmsolar farm47.7approved, not builtupdated Jan 2026Feb 2023granted Dec 2025Jan 2026North Warwickshire9.3
Leamington Road, Princethorpe - Ash Tree Solar Photovoltaic Arrayssolar farmsolar farm16.8approved, not builtupdated Dec 2025May 2024granted Aug 2025Dec 2025Rugby9.9
Bungalow Farm, Smeaton Lanebattery storagebattery storage60application submittedupdated Feb 2025Jan 2025—Feb 2025Rugby9.9
Bungalow Farm, Smeaton Lanebattery storagebattery storage60application submittedupdated Feb 2025Jan 2025—Feb 2025Rugby9.9
Smaller schemes under 1 MW, mostly rooftop solar (30)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cycle Works Buildingrooftop solarrooftop solar—approved, not builtupdated Jan 2025Oct 2024granted Nov 2024Jan 2025Coventry0.3
Sidney Stringer Academy, Primrose Hill Streetrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Sep 2025granted Sep 2025Jan 2026Coventry0.5
City College, Swanswell Streetrooftop solarrooftop solar0.5approved, not builtupdated Jan 2026Sep 2025granted Sep 2025Jan 2026Coventry0.5
Coventry Universityrooftop solarrooftop solar—approved, not builtupdated Jan 2025Oct 2024granted Nov 2024Jan 2025Coventry0.6
Coventry University, Decarbonisation Scheme - The Hubrooftop solarrooftop solar—approved, not builtupdated Feb 2025Oct 2024granted Nov 2024Feb 2025Coventry0.6
Sky Dome Solar Photovoltaicsrooftop solarrooftop solar0.4approved, not builtupdated Aug 2021Jun 2021granted Jul 2021Aug 2021Coventry0.8
Brose, Courtaulds Wayrooftop solarrooftop solar0.4approved, not builtupdated Jan 2025Oct 2024granted Nov 2024Jan 2025Coventry1.7
Manor Park Primary School, Ulverscroft Roadrooftop solarrooftop solar0.2application submittedMay 2026——Coventry2.0
Alan Higgs Centre, Allard Wayrooftop solarrooftop solar0.4approved, not builtupdated Feb 2025Nov 2024granted Dec 2024Feb 2025Coventry2.7
Coventry Sports Foundation, Bell Green Roadrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Jan 2025granted Jan 2025Mar 2025Coventry2.8
Ravensdale Primary School, Ravensdale Roadrooftop solarrooftop solar0.2application submittedJun 2026——Coventry2.8
Mercedes Benz Coventry, John Wigley Wayrooftop solarrooftop solar0.2approved, not builtupdated Nov 2022Sep 2022granted Oct 2022Nov 2022Coventry2.9
Caludon castle school, Axholme Roadrooftop solarrooftop solar0.3approved, not builtupdated Feb 2024Dec 2023granted Feb 2024Feb 2024Coventry3.7
Moat House Leisure & Neighbourhood Centre, Winston Avenuerooftop solarrooftop solar0.3application submittedupdated Nov 2024Sep 2024—Nov 2024Coventry4.1
UKBIC, Rowley Roadrooftop solarrooftop solar—application submitted may be out of dateupdated Sep 2023Aug 2023—Sep 2023Warwick4.2
Skipworth Roadrooftop solarrooftop solar0.8approved, not builtupdated Mar 2022Feb 2022granted Mar 2022Mar 2022Coventry4.7
Unit 1, Mallory Way, Longfordrooftop solarrooftop solar0.3refusedupdated Nov 2022Aug 2022refused Nov 2022Nov 2022Nuneaton and Bedworth4.8
Ree Automotive Uk, Siskin Driverooftop solarrooftop solar0.6approved, not builtupdated Mar 2025Feb 2025granted Apr 2025Mar 2025Warwick4.9
Unit 13, Central Boulevard Solar photovoltaicsrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Coventry5.2
Unit 12, Central Boulevardrooftop solarrooftop solar0.8approved, not builtupdated Apr 2026Jan 2026granted Feb 2026Apr 2026Coventry5.2
Siskin Parkway East, Middlemarch Business Parkrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Mar 2022Dec 2022granted Feb 2023Mar 2022Warwick5.6
Canute Haulage Group, Siskin Parkway Eastrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024May 2024granted Jun 2024Jul 2024Warwick5.7
Bowling Alley, Olivier Wayrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Coventry5.7
Batleys Plc, Gielgud Wayrooftop solarrooftop solar0.1approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Coventry5.9
Automotive Trim Developments, Priory Millrooftop solarrooftop solar0.4approved, not builtupdated Jun 2024Apr 2024granted Jun 2024Jun 2024Coventry6.2
Sainsburys Supermarketsrooftop solarrooftop solar0.3approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Rugby7.0
Sainsburys, Draken Driverooftop solarrooftop solar0.3approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Rugby7.0
Brose, Colliery Lane Northrooftop solarrooftop solar0.6refusedupdated Jan 2025Oct 2024refused Nov 2024Jan 2025Nuneaton and Bedworth7.1
Corley Smorral Lanebattery storagebattery storage—approved, not built may be out of dateupdated Nov 2021Nov 2021granted Jul 2022Nov 2021Nuneaton and Bedworth7.7
Castle Farm Recreation Ground, Fishponds Roadrooftop solarrooftop solar—approved, not builtupdated Apr 2025Feb 2025granted Apr 2025Apr 2025Warwick9.4

Distance from the average position of the CV1 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm122604179
Rooftop solar31424029
Battery storage20910101,242

MW in pipeline: pending, approved and under-construction capacity.

How Coventry decides solar, wind and battery applications

ApplicationsCoventryUK
Decided applications (solar, wind, battery)2310,236
Refused2 (9%)19%
Solar refused2 of 2112%
Battery storage refused0 of 216%
Median time from submission to decision7.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Coventry

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CV1, 10 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.