Hill House Farm, Coventry Road (20 MW battery storage)

Hill House Farm, Coventry Road is a 20 MW battery storage project in Solihull, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 14 April 2025, no decision recorded; the record was last updated on 17 June 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
application submittedstatus in REPD
17 June 2025record last updated
Solihullcouncil area

Planning timeline

DateStage
14 April 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
application submitted
Record last updated
17 June 2025
Operator or applicant
Root Power South Limited
Planning authority
Solihull
Planning application reference
PL/2025/00806/PPFL
Address (REPD)
Hill House Farm, Coventry Road, Berkswell
Council area (by location)
Solihull
Name in REPD
Hill House Farm, Coventry Road - Battery Energy Storage System
REPD reference
18866

Who decides

ApplicationsSolihullUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused4 of 2212%
Battery storage refused4 of 816%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed4 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Broad Lanesolar farm8.5refused on appeal1.1
Benton Green Lanebattery storage70application submitted1.1
Tanners Lanebattery storage30approved, not built1.8
Beechwood Farm, Hodgetts Lanebattery storage57approved, not built2.4
Beechwood Farm, Hodgetts Lanebattery storage57application submitted2.4
Nailcote Farmsolar farm18refused2.4
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage49.9application submitted2.7
Little Beanit Farm, Balsall Commonbattery storage200under construction3.0
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage49.9application submitted3.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4131, -1.6257).