Energy Projects Near You

Broad Lane (8.5 MW solar farm)

Broad Lane is an 8.5 MW solar farm project in Coventry, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 1 March 2017; the record was last updated on 29 March 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.5 MWsolar farm
refused on appealstatus in REPD
29 March 2017record last updated
Coventrycouncil area

Planning timeline

DateStage
14 September 2015Application submitted
8 February 2016Refused by the planning authority
13 September 2016Appeal lodged
1 March 2017Appeal refused

Project details

Technology
solar farm
Capacity
8.5 MW
Status (REPD)
refused on appeal
Record last updated
29 March 2017
Operator or applicant
Earthworm Energy
Planning authority
Solihull
Planning application reference
PL/2015/51636/PPFL
Appeal reference
APP/Q4625/W/16/3155025
Site area
13.9 ha
Address (REPD)
Hawkshurst Moor Farm, Broad Lane, Coventry
Council area (by location)
Coventry
Time to decision
21 weeks
REPD reference
5843

Who decides

ApplicationsSolihullUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused4 of 2212%
Battery storage refused4 of 816%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed4 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hill House Farm, Coventry Roadbattery storage20application submitted1.1
Benton Green Lanebattery storage70application submitted1.5
Tanners Lanebattery storage30approved, not built1.5
Nailcote Farmsolar farm18refused2.5
Beechwood Farm, Hodgetts Lanebattery storage57application submitted2.8
Beechwood Farm, Hodgetts Lanebattery storage57approved, not built2.8
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage49.9application submitted2.9
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage49.9approved, not built3.3
Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage49.9application submitted3.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4156, -1.6107).