Park House Farm, Meriden Road Solar Farm (47.7 MW)
Park House Farm, Meriden Road Solar Farm is a 47.7 MW solar farm project in North Warwickshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 December 2025, not yet built; the record was last updated on 26 January 2026.
47.7 MWsolar farm
approved, not builtstatus in REPD
26 January 2026record last updated
North Warwickshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 24 February 2023 | Application submitted |
| 10 July 2024 | Refused by the planning authority |
| 15 October 2024 | Appeal lodged |
| 11 December 2025 | Planning permission granted |
| 11 December 2025 | Appeal allowed |
Project details
- Technology
- solar farm
- Capacity
- 47.7 MW
- Status (REPD)
- approved, not built
- Record last updated
- 26 January 2026
- Operator or applicant
- Enviromena Asset Management UK Limited
- Planning authority
- North Warwickshire
- Planning application reference
- PAP/2023/0071
- Appeal reference
- APP/R3705/W/24/3349391
- Site area
- 61.0 ha
- Address (REPD)
- 800m S/O Park House Farm, Meriden Road, Fillongley, Coventry
- Council area (by location)
- North Warwickshire
- Time to decision
- 146 weeks
- Name in REPD
- Park House Farm, Meriden Road - Solar Farm
- REPD reference
- 13440
Who decides
| Applications | North Warwickshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 32 | 10,236 |
| Refused | 3 (9%) | 19% |
| Solar refused | 2 of 23 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 0 of 8 | 16% |
| Median time from submission to decision | 16.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Land South of Pogmore Spinney | solar farm | 5 | operational | 2.9 |
| Corley Smorral Lane - Photovoltaic Solar Arrays | solar farm | 16.5 | approved, not built | 3.6 |
| Park Lane, Astley Solar PV Farm | solar farm | 30 | approved, not built | 3.8 |
| Vauls Farm, Astley Lane Solar Farm | solar farm | 16 | approved, not built | 5.0 |
| Newgate Coolliery Solar Farm & Battery Storage | solar farm | 6 | application submitted | 6.2 |
| Broad Lane | solar farm | 8.5 | refused on appeal | 6.4 |
| Hill House Farm, Coventry Road | battery storage | 20 | application submitted | 6.9 |
| Mcdonnell Drive, Exhall | battery storage | 30 | approved, not built | 7.4 |
| Benton Green Lane | battery storage | 70 | application submitted | 7.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4722, -1.5962).