Solar, wind and battery projects near Birmingham (B46)

50 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of B46 (North Warwickshire): 7 are waiting for a planning decision, 37 approved but not yet running, 1 operational. The largest live scheme is Hams Hall (400 MW battery storage, under construction since 1 January 2025), 3.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50projects within 10 km
7awaiting a decision
37approved, not running
1operational

Projects within 10 km of B46

Projects of 1 MW and more (24)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
BAC Jaguar Land Rover Battery Assembly Centre, Canton Lanerooftop solarrooftop solar2.2approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024North Warwickshire2.5
Lichfield Road, Watton Lanebattery storagebattery storage49.9approved, not builtupdated Apr 2024Feb 2023granted Mar 2024Apr 2024North Warwickshire2.6
Hams Hallbattery storagebattery storage400under constructionupdated Mar 2026Aug 2021granted Mar 2022Mar 2026North Warwickshire3.3
Coton Roadsolar farmsolar farm3approved, not built may be out of dateupdated Oct 2021Oct 2021granted Mar 2022Oct 2021North Warwickshire3.8
WHS Plastics, Water Orton Lanerooftop solarrooftop solar1.1approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025North Warwickshire4.1
Hams Hall, Hams Lanebattery storagebattery storage98approved, not builtupdated Dec 2025May 2025granted Oct 2025Dec 2025North Warwickshire4.2
Marston Fields Farm, Kingsbury Roadbattery storagebattery storage10approved, not builtupdated Jul 2025Dec 2024granted Jun 2025Jul 2025North Warwickshire4.6
Wishaw Lane, Sutton Coldfieldbattery storagebattery storage50application submittedupdated Feb 2025Dec 2024—Feb 2025Birmingham5.1
Marston Sewerage Pumping Station, Bodymoor Heath Lanebattery storagebattery storage50application submittedupdated Jul 2025May 2025—Jul 2025North Warwickshire5.4
Holly Lane Energy Park Solar Farm & Battery Storagesolar farmsolar farm25approved, not builtupdated Feb 2026Sep 2023granted Jan 2025Feb 2026Solihull5.9
Camp Farm, Knowle Hillbattery storagebattery storage50approved, not builtupdated Sep 2025Jan 2025granted Aug 2025Sep 2025North Warwickshire6.2
Camp Farm, Knowle Hill Solar Farmsolar farmsolar farm49.9approved, not builtupdated Sep 2025Jan 2025granted Aug 2025Sep 2025North Warwickshire6.2
NEC, Birminghamrooftop solarrooftop solar3.9abandonedupdated Mar 2018Aug 2015granted Oct 2015Mar 2018Solihull6.6
Land South of Pogmore Spinneysolar farmsolar farm5operationalupdated May 2017Jul 2015granted Feb 2016May 2017North Warwickshire6.6
Maybrook Road Battery facilitybattery storagebattery storage13.1approved, not builtupdated Apr 2022Mar 2022granted Aug 2022Apr 2022Birmingham6.7
Park House Farm, Meriden Road Solar Farmsolar farmsolar farm47.7approved, not builtupdated Jan 2026Feb 2023granted Dec 2025Jan 2026North Warwickshire7.8
Fort Shopping Park, Fort Parkwayrooftop solarrooftop solar1.6approved, not builtupdated Oct 2023Aug 2023granted Sep 2023Oct 2023Birmingham8.7
Wienerberger Brick Workswind turbinewind turbine2.5refused on appealupdated Aug 2015Jul 2013refused Jan 2014Aug 2015North Warwickshire9.0
Kingsbury Pallets, Rush Lanerooftop solarrooftop solar3application submittedupdated May 2026Apr 2026—May 2026North Warwickshire9.0
Park Lane, Astley Solar PV Farmsolar farmsolar farm30approved, not built may be out of dateupdated Jun 2025Dec 2021granted Jul 2022Jun 2025North Warwickshire9.1
Solar Panels at Woodhouse Farmsolar farmsolar farm49.9application submittedupdated Sep 2025Jul 2025—Sep 2025Solihull9.5
Castle Hills Solar Farmsolar farmsolar farm5application submittedupdated Sep 2025Jul 2025—Sep 2025Solihull9.5
Copes Rough Wood, Lower House Lane Solar Farmsolar farmsolar farm5approved, not builtupdated Feb 2026Sep 2022granted Sep 2023Feb 2026North Warwickshire9.7
Lower House Lanesolar farmsolar farm4refusedupdated Jan 2016Oct 2015refused Dec 2015Jan 2016North Warwickshire9.8
Smaller schemes under 1 MW, mostly rooftop solar (26)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Highway Point, Gorsey Lanerooftop solarrooftop solar0.6approved, not builtupdated Oct 2023Jul 2023granted Sep 2023Oct 2023North Warwickshire1.5
Coleshill Food Waste, Ad Plantmarconi Wayrooftop solarrooftop solar0.2approved, not builtupdated Feb 2024Dec 2023granted Jan 2024Feb 2024North Warwickshire1.5
Hams Hall National Distribution Park, Faraday Avenuerooftop solarrooftop solar0.3approved, not builtupdated Jan 2024Dec 2023granted Jan 2024Jan 2024North Warwickshire1.7
Expeditors, Coleshill Solar Panels, Unit 17Arooftop solarrooftop solar0.1approved, not builtupdated Sep 2025Aug 2025granted Aug 2025Sep 2025North Warwickshire2.5
Bishop Wilson Ce Primary School, Craig Croftrooftop solarrooftop solar0.4approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026Solihull4.1
Cembre Limited Dunton Park, Kingsbury Roadrooftop solarrooftop solar0.9approved, not builtupdated Apr 2023Mar 2023granted Apr 2023Apr 2023North Warwickshire4.2
Tudor Grange Academy, Kingshurst Cooks Lane - Photovoltaic Solar Panelsrooftop solarrooftop solar0.4approved, not builtupdated Dec 2023Sep 2023granted Nov 2023Dec 2023Solihull4.2
Park Hall Academy, Water Orton Roadrooftop solarrooftop solar0.3approved, not builtApr 2026granted Jun 2026—Solihull4.8
Melbicks Garden Centre, Chester Roadrooftop solarrooftop solar0.4approved, not built may be out of dateupdated Nov 2022Sep 2022granted Nov 2022Nov 2022North Warwickshire5.3
Progress Way, Marston Greenrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024Solihull5.4
Unit B, Progress Wayrooftop solarrooftop solar—approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024Solihull5.4
Hozelock, Midpoint Parkrooftop solarrooftop solar0.2application submittedMay 2026——Birmingham5.7
Premier Paper, Midpoint Parkrooftop solarrooftop solar0.3approved, not builtupdated Apr 2026Dec 2025granted Jan 2026Apr 2026Birmingham5.8
The Palletline Centre, Starley Way - Roof Mounted Solar PV arrayrooftop solarrooftop solar0.1approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Solihull6.1
Vertik-Al,Yardley Brook Industrial Parkrooftop solarrooftop solar0.5approved, not builtupdated Jan 2023Nov 2022granted Dec 2022Jan 2023Birmingham6.3
Kingsbury High School, Tamworth Road -Solar Panelsrooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Nov 2025granted Jan 2026Apr 2026North Warwickshire6.4
Birmingham Airport, Diamond Houserooftop solarrooftop solar1approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Solihull6.9
Buzz Bingo, Kingsbury Roadrooftop solarrooftop solar0.5approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Birmingham7.5
Eagle 3, Hatchford Wayrooftop solarrooftop solar0.3application submittedupdated May 2026Mar 2026—May 2026Birmingham7.9
Eagle Two, Hatchford Wayrooftop solarrooftop solar0.3application withdrawnupdated Jan 2026Jan 2025—Jan 2026Birmingham7.9
Tesco Stores, Coleshill Roadrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Dec 2024granted Feb 2025Feb 2025Birmingham8.5
Hampton Manorsolar farmsolar farm0.3refusedupdated Jun 2020Sep 2019refused Apr 2020Jun 2020Solihull9.0
Park Lane, Astleybattery storagebattery storage—approved, not built may be out of dateupdated Jun 2025Dec 2021granted Jul 2022Jun 2025North Warwickshire9.1
Mercedes benz garage, Bromford Lanerooftop solarrooftop solar0.3approved, not builtupdated May 2023Feb 2023granted Mar 2023May 2023Birmingham9.4
Birmingham Heartlands Hospital - Roof Top Solar Farmrooftop solarrooftop solar0.6approved, not builtupdated Jul 2022Jun 2022granted Oct 2022Jul 2022Birmingham9.6
Jaguar Land Rover, Lode Lane – Battery Storage Unitbattery storagebattery storage—approved, not built may be out of dateupdated Jul 2023Apr 2023granted Jul 2023Jul 2023Solihull9.9

Distance from the average position of the B46 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm112612216
Rooftop solar283230016
Wind turbine100010
Battery storage102800721

MW in pipeline: pending, approved and under-construction capacity.

How North Warwickshire decides solar, wind and battery applications

ApplicationsNorth WarwickshireUK
Decided applications (solar, wind, battery)3210,236
Refused3 (9%)19%
Solar refused2 of 2312%
Onshore wind refused1 of 145%
Battery storage refused0 of 816%
Median time from submission to decision16.4 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

All projects in North Warwickshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near B46, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.