Energy Projects Near You

Hams Hall (400 MW battery storage)

Hams Hall is a 400 MW battery storage project in North Warwickshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 January 2025; the record was last updated on 9 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWbattery storage
under constructionstatus in REPD
9 March 2026record last updated
North Warwickshirecouncil area

Planning timeline

DateStage
5 August 2021Application submitted
4 March 2022Planning permission granted
1 January 2025Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
400 MW
Status (REPD)
under construction
Record last updated
9 March 2026
Operator or applicant
Welbar Energy Storage Limited / Penso Power (BW ESS)
Planning authority
North Warwickshire
Planning application reference
PAP/2021/0473
Address (REPD)
East & Se/O Dunton Hall, Kingsbury Road, Curdworth, Sutton Coldfield
Council area (by location)
North Warwickshire
Time to decision
30 weeks
Name in REPD
Hams Hall - Battery Energy Storage System
REPD reference
9427

Who decides

ApplicationsNorth WarwickshireUK
Decided applications (solar, wind, battery)3210,236
Refused3 (9%)19%
Solar refused2 of 2312%
Onshore wind refused1 of 145%
Battery storage refused0 of 816%
Median time from submission to decision16.4 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hams Hall, Hams Lanebattery storage98approved, not built1.5
Marston Fields Farm, Kingsbury Roadbattery storage10approved, not built1.9
Lichfield Road, Watton Lanebattery storage49.9approved, not built2.4
Marston Sewerage Pumping Station, Bodymoor Heath Lanebattery storage50application submitted2.6
Wishaw Lane, Sutton Coldfieldbattery storage50application submitted2.7
Camp Farm, Knowle Hillbattery storage50approved, not built4.9
Camp Farm, Knowle Hill Solar Farmsolar farm49.9approved, not built4.9
Maybrook Road Battery facilitybattery storage13.1approved, not built5.0
Holly Lane Energy Park Solar Farm & Battery Storagesolar farm25approved, not built7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5359, -1.7153).