Maybrook Road Battery facility (13.1 MW)

Maybrook Road Battery facility is a 13.1 MW battery storage project in Birmingham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 8 August 2022, not yet built; the record was last updated on 19 April 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.1 MWbattery storage
approved, not builtstatus in REPD
19 April 2022record last updated
Birminghamcouncil area

Planning timeline

DateStage
7 March 2022Application submitted
8 August 2022Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
13.1 MW
Status (REPD)
approved, not built
Record last updated
19 April 2022
Operator or applicant
Conrad Energy (Develeopments) Limited
Planning authority
Birmingham
Planning application reference
2022/01927/PA
Address (REPD)
Maybrook Business Park - Unit 6 Maybrook Road Sutton Coldfield
Council area (by location)
Birmingham
Time to decision
22 weeks
Name in REPD
Maybrook Road - Battery facility
REPD reference
11008

Who decides

ApplicationsBirminghamUK
Decided applications (solar, wind, battery)5110,236
Refused1 (2%)19%
Solar refused1 of 4712%
Battery storage refused0 of 416%
Median time from submission to decision6.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

UK: all UK planning authorities. Counted under these REPD planning authority names: Birmingham, Birmingham Ladywood.

Other large projects within 10 km

ProjectTypeMWStatuskm
Wishaw Lane, Sutton Coldfieldbattery storage50application submitted2.4
Lichfield Road, Watton Lanebattery storage49.9approved, not built4.2
Hams Hallbattery storage400under construction5.0
Hams Hall, Hams Lanebattery storage98approved, not built6.1
Marston Fields Farm, Kingsbury Roadbattery storage10approved, not built6.5
Marston Sewerage Pumping Station, Bodymoor Heath Lanebattery storage50application submitted6.7
Holly Lane Energy Park Solar Farm & Battery Storagesolar farm25approved, not built6.9
Camp Farm, Knowle Hill Solar Farmsolar farm49.9approved, not built9.6
Camp Farm, Knowle Hillbattery storage50approved, not built9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5296, -1.7883).