Camp Farm, Knowle Hill Solar Farm (49.9 MW)

Camp Farm, Knowle Hill Solar Farm is a 49.9 MW solar farm project in North Warwickshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 18 August 2025, not yet built; the record was last updated on 10 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
10 September 2025record last updated
North Warwickshirecouncil area

Planning timeline

DateStage
6 January 2025Application submitted
18 August 2025Planning permission granted
18 August 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
10 September 2025
Operator or applicant
Ampyr Solar Europe
Planning authority
North Warwickshire
Planning application reference
PAP/2024/0586
Site area
75.0 ha
Address (REPD)
400 Metres W/O Camp Farm, Knowle Hill, Hurley, Atherstone
Council area (by location)
North Warwickshire
Time to decision
32 weeks
Name in REPD
Camp Farm, Knowle Hill - Solar Farm
REPD reference
17961

Recorded together with Camp Farm, Knowle Hill (50 MW battery storage, approved, not built).

Who decides

ApplicationsNorth WarwickshireUK
Decided applications (solar, wind, battery)3210,236
Refused3 (9%)19%
Solar refused2 of 2312%
Onshore wind refused1 of 145%
Battery storage refused0 of 816%
Median time from submission to decision16.4 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Marston Sewerage Pumping Station, Bodymoor Heath Lanebattery storage50application submitted3.1
Marston Fields Farm, Kingsbury Roadbattery storage10approved, not built3.2
Hams Hall, Hams Lanebattery storage98approved, not built3.5
Copes Rough Wood, Lower House Lane Solar Farmsolar farm5approved, not built3.6
Hams Hallbattery storage400under construction4.9
Lichfield Road, Watton Lanebattery storage49.9approved, not built7.0
Wishaw Lane, Sutton Coldfieldbattery storage50application submitted7.2
Land South of Pogmore Spinneysolar farm5operational7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5585, -1.654).