Land South of Pogmore Spinney (5 MW solar farm)

Land South of Pogmore Spinney is a 5 MW solar farm project in North Warwickshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2017; the record was last updated on 16 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
16 May 2017record last updated
North Warwickshirecouncil area

Planning timeline

DateStage
24 July 2015Application submitted
29 February 2016Planning permission granted
23 January 2017Construction started
30 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
16 May 2017
Operator or applicant
Murex Energy
Planning authority
North Warwickshire
Planning application reference
PAP/2015/0459
Site area
5.2 ha
Address (REPD)
Land South of Pogmore Spinney, Merevale Lane, Atherstone, Warwickshire
Council area (by location)
North Warwickshire
Time to decision
31 weeks
REPD reference
5391

Who decides

ApplicationsNorth WarwickshireUK
Decided applications (solar, wind, battery)3210,236
Refused3 (9%)19%
Solar refused2 of 2312%
Onshore wind refused1 of 145%
Battery storage refused0 of 816%
Median time from submission to decision16.4 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Park Lane, Astley Solar PV Farmsolar farm30approved, not built2.5
Park House Farm, Meriden Road Solar Farmsolar farm47.7approved, not built2.9
Corley Smorral Lane - Photovoltaic Solar Arrayssolar farm16.5approved, not built4.6
Vauls Farm, Astley Lane Solar Farmsolar farm16approved, not built5.1
Newgate Coolliery Solar Farm & Battery Storagesolar farm6application submitted6.7
Camp Farm, Knowle Hillbattery storage50approved, not built7.6
Camp Farm, Knowle Hill Solar Farmsolar farm49.9approved, not built7.6
Mcdonnell Drive, Exhallbattery storage30approved, not built8.6
Hams Hall, Hams Lanebattery storage98approved, not built8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4985, -1.5989).