Solar, wind and battery projects near Atherstone (CV9)
26 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CV9 (North Warwickshire): 5 are waiting for a planning decision, 16 approved but not yet running, 3 operational. The largest live scheme is Camp Farm, Knowle Hill (50 MW battery storage, approved on 18 August 2025, not yet built), 6.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CV9
Projects of 1 MW and more (15)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Atherstonesolar farm | solar farm | 14.7 | operationalupdated Jul 2015 | Sep 2014 | granted Nov 2014 | Jul 2015 | North Warwickshire | 3.0 |
| Ld NW Of Ratcliffe House Farmsolar farm | solar farm | 3.5 | operationalupdated Feb 2016 | May 2015 | granted Aug 2015 | Feb 2016 | Hinckley and Bosworth | 3.8 |
| Copes Rough Wood, Lower House Lane Solar Farmsolar farm | solar farm | 5 | approved, not builtupdated Feb 2026 | Sep 2022 | granted Sep 2023 | Feb 2026 | North Warwickshire | 4.1 |
| Lower House Lanesolar farm | solar farm | 4 | refusedupdated Jan 2016 | Oct 2015 | refused Dec 2015 | Jan 2016 | North Warwickshire | 4.1 |
| Business Park, Meridian Driverooftop solar | rooftop solar | 1.5 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | North Warwickshire | 4.4 |
| Euro Car Parts Solar Panels & Battery Storagerooftop solar | rooftop solar | 3 | approved, not builtupdated Oct 2023 | Sep 2023 | granted Oct 2023 | Oct 2023 | North Warwickshire | 4.5 |
| Camp Farm, Knowle Hillbattery storage | battery storage | 50 | approved, not builtupdated Sep 2025 | Jan 2025 | granted Aug 2025 | Sep 2025 | North Warwickshire | 6.9 |
| Camp Farm, Knowle Hill Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Sep 2025 | Jan 2025 | granted Aug 2025 | Sep 2025 | North Warwickshire | 6.9 |
| Horiba Mira, Mira Drivesolar farm | solar farm | 7 | operationalupdated May 2026 | Sep 2022 | granted Feb 2023 | May 2026 | Hinckley and Bosworth | 7.7 |
| Wienerberger Brick Workswind turbine | wind turbine | 2.5 | refused on appealupdated Aug 2015 | Jul 2013 | refused Jan 2014 | Aug 2015 | North Warwickshire | 8.0 |
| Kingsbury Pallets, Rush Lanerooftop solar | rooftop solar | 3 | application submittedupdated May 2026 | Apr 2026 | — | May 2026 | North Warwickshire | 8.1 |
| Amington Hall Farm Solar Farmsolar farm | solar farm | 30 | approved, not builtupdated Mar 2025 | Mar 2023 | granted Feb 2025 | Mar 2025 | Tamworth | 8.3 |
| Weddington Roadbattery storage | battery storage | 49.9 | approved, not builtupdated Jul 2026 | Aug 2024 | granted Feb 2026 | Jul 2026 | Nuneaton and Bedworth | 9.1 |
| Park Lane, Astley Solar PV Farmsolar farm | solar farm | 30 | approved, not built may be out of dateupdated Jun 2025 | Dec 2021 | granted Jul 2022 | Jun 2025 | North Warwickshire | 9.7 |
| Marston Sewerage Pumping Station, Bodymoor Heath Lanebattery storage | battery storage | 50 | application submittedupdated Jul 2025 | May 2025 | — | Jul 2025 | North Warwickshire | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Meridian Drive, Dordonrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2022 | Mar 2022 | granted May 2022 | Mar 2022 | North Warwickshire | 4.3 |
| Bristan, Pooley Hall Driverooftop solar | rooftop solar | 0.7 | approved, not builtupdated Oct 2023 | Aug 2023 | granted Oct 2023 | Oct 2023 | North Warwickshire | 4.4 |
| Euro Car Parts Solar Panels & Battery Storagebattery storage | battery storage | — | approved, not builtupdated Oct 2023 | Sep 2023 | granted Oct 2023 | Oct 2023 | North Warwickshire | 4.5 |
| Tamworth Logistics Park, Dordonrooftop solar | rooftop solar | 0.5 | application submittedupdated Feb 2026 | Jan 2026 | — | Feb 2026 | North Warwickshire | 5.3 |
| Manor Park, Twycrosssolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated Oct 2021 | Jul 2021 | granted Sep 2021 | Oct 2021 | Hinckley and Bosworth | 6.7 |
| Marlborough Way, Belgraverooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2022 | Mar 2022 | granted May 2022 | Mar 2022 | Tamworth | 8.1 |
| Two Gates Trading Estate, Watling Streetrooftop solar | rooftop solar | 0.2 | application submitted | Jun 2026 | — | — | Tamworth | 8.3 |
| Kingsbury High School, Tamworth Road -Solar Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2026 | Nov 2025 | granted Jan 2026 | Apr 2026 | North Warwickshire | 8.5 |
| The Nuneaton Academy, Radnor Driverooftop solar | rooftop solar | 0.5 | application submittedupdated May 2026 | Mar 2026 | — | May 2026 | Nuneaton and Bedworth | 9.0 |
| Park Lane, Astleybattery storage | battery storage | — | approved, not built may be out of dateupdated Jun 2025 | Dec 2021 | granted Jul 2022 | Jun 2025 | North Warwickshire | 9.7 |
| North Warwickshire College, Hinckley Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Nov 2023 | Jul 2023 | granted Sep 2023 | Nov 2023 | Nuneaton and Bedworth | 9.8 |
Distance from the average position of the CV9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 9 | 0 | 5 | 3 | 1 | 115 |
| Rooftop solar | 11 | 4 | 7 | 0 | 0 | 10.3 |
| Wind turbine | 1 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 5 | 1 | 4 | 0 | 0 | 150 |
MW in pipeline: pending, approved and under-construction capacity.
How North Warwickshire decides solar, wind and battery applications
| Applications | North Warwickshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 32 | 10,236 |
| Refused | 3 (9%) | 19% |
| Solar refused | 2 of 23 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 0 of 8 | 16% |
| Median time from submission to decision | 16.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 1 | — |
All projects in North Warwickshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CV9, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.