Atherstone (14.7 MW solar farm)

Atherstone is a 14.7 MW solar farm project in North Warwickshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 31 July 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.7 MWsolar farm
operationalstatus in REPD
31 July 2015record last updated
North Warwickshirecouncil area

Planning timeline

DateStage
12 September 2014Application submitted
14 November 2014Planning permission granted
1 January 2015Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
14.7 MW
Status (REPD)
operational
Record last updated
31 July 2015
Operator or applicant
Foresight Solar Fund
Planning authority
North Warwickshire
Planning application reference
PAP/2014/0483
Site area
32.1 ha
Address (REPD)
Land East Of Grendon House Farm Warton Lane Grendon
Council area (by location)
North Warwickshire
Time to decision
9 weeks
REPD reference
2278

Who decides

ApplicationsNorth WarwickshireUK
Decided applications (solar, wind, battery)3210,236
Refused3 (9%)19%
Solar refused2 of 2312%
Onshore wind refused1 of 145%
Battery storage refused0 of 816%
Median time from submission to decision16.4 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Copes Rough Wood, Lower House Lane Solar Farmsolar farm5approved, not built5.3
Amington Hall Farm Solar Farmsolar farm30approved, not built6.7
Camp Farm, Knowle Hill Solar Farmsolar farm49.9approved, not built8.8
Camp Farm, Knowle Hillbattery storage50approved, not built8.8
Highfields Farm, Clifton Lanesolar farm61.9under construction9.0
Horiba Mira, Mira Drivesolar farm7operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6131, -1.559).