Amington Hall Farm Solar Farm (30 MW)

Amington Hall Farm Solar Farm is a 30 MW solar farm project in Tamworth, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 February 2025, not yet built; the record was last updated on 10 March 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
approved, not builtstatus in REPD
10 March 2025record last updated
Tamworthcouncil area

Planning timeline

DateStage
2 March 2023Application submitted
26 February 2025Planning permission granted

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
10 March 2025
Operator or applicant
Tamworth Solar Limited
Planning authority
Tamworth
Planning application reference
25/00095/PA52
Address (REPD)
east of Amington Hall Farm
Council area (by location)
Tamworth
Time to decision
104 weeks
Contracts for Difference
AR6
Name in REPD
Amington Hall Farm - Solar Farm
REPD reference
13371

Who decides

Tamworth has 4 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Highfields Farm, Clifton Lanesolar farm61.9under construction3.9
Haunton Solar Farmsolar farm49.9approved, not built5.6
Copes Rough Wood, Lower House Lane Solar Farmsolar farm5approved, not built6.4
Atherstonesolar farm14.7operational6.7
Camp Farm, Knowle Hillbattery storage50approved, not built9.1
Camp Farm, Knowle Hill Solar Farmsolar farm49.9approved, not built9.1
Marston Sewerage Pumping Station, Bodymoor Heath Lanebattery storage50application submitted9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6399, -1.6474).