Energy Projects Near You

Highfields Farm, Clifton Lane (61.9 MW solar farm)

Highfields Farm, Clifton Lane is a 61.9 MW solar farm project in Lichfield, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 June 2026; the record was last updated on 13 July 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

61.9 MWsolar farm
under constructionstatus in REPD
13 July 2026record last updated
Lichfieldcouncil area

Planning timeline

DateStage
17 January 2022Application submitted
11 July 2023Planning permission granted
1 June 2026Construction started

Project details

Technology
solar farm
Capacity
61.9 MW
Status (REPD)
under construction
Record last updated
13 July 2026
Operator or applicant
Elgin Energy ESCO Limited
Planning authority
Lichfield
Planning application reference
22/00110/FULM
Address (REPD)
Highfields Farm Clifton Lane Tamworth
Council area (by location)
Lichfield
Time to decision
77 weeks
Contracts for Difference
AR6
Name in REPD
Highfields Farm, Clifton Lane - Solar Panels
REPD reference
10477

Who decides

ApplicationsLichfieldUK
Decided applications (solar, wind, battery)1310,236
Refused2 (15%)19%
Solar refused0 of 1012%
Onshore wind refused1 of 145%
Battery storage refused1 of 216%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Haunton Solar Farmsolar farm49.9approved, not built1.8
Amington Hall Farm Solar Farmsolar farm30approved, not built3.9
Solar Farm & Battery Storage at W/O Rosliston & E/O Walton on Trentsolar farm138approved, not built8.2
Shortheath Solar Parksolar farm5operational8.8
Atherstonesolar farm14.7operational9.0
Drakelowbattery storage1,000application submitted9.8
Mount Road, Castle Gresleybattery storage20approved, not built9.9
Fairfields Energy Storage Systembattery storage1,025approved, not built10.0
Barn Farm - Batter Energy Storage Facilitybattery storage200approved, not built10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.675, -1.6449).