Energy Projects Near You

Solar Farm & Battery Storage at W/O Rosliston & E/O Walton on Trent (138 MW)

Solar Farm & Battery Storage at W/O Rosliston & E/O Walton on Trent is a 138 MW solar farm project in South Derbyshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 June 2025, not yet built; the record was last updated on 24 June 2025. As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010122).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

138 MWsolar farm
approved, not builtstatus in REPD
24 June 2025record last updated
South Derbyshirecouncil area

Planning timeline

DateStage
8 February 2024Application submitted
19 June 2025Development consent granted (Secretary of State)

Project details

Technology
solar farm
Capacity
138 MW
Status (REPD)
approved, not built
Record last updated
24 June 2025
Operator or applicant
BayWa r.e. UK Limited
Planning authority
The Planning Inspectorate - National Infrastructure
Planning application reference
EN010122
Site area
218.5 ha
Address (REPD)
W/O Rosliston & E/O Walton on Trent, Swadlincote
Council area (by location)
South Derbyshire
Time to decision
71 weeks
Name in REPD
Oaklands Solar Farm Project - Solar Farm & Battery Storage
REPD reference
9546

The scheme also includes 37.5 MW of battery storage, recorded separately in REPD (approved, not built).

Official project record at the Planning Inspectorate (EN010122)

Who decides

As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010122). All Energy Secretary decisions on solar and wind farms. The Planning Inspectorate - National Infrastructure refused 7% of 46 decided solar, wind and battery applications in REPD (median 73 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Caldwell Roadbattery storage90approved, not built2.5
Fairfields Energy Storage Systembattery storage1,025approved, not built2.8
Barn Farm - Batter Energy Storage Facilitybattery storage200approved, not built2.8
Breach Farm Energy Barnbattery storage40approved, not built3.0
Drakelow Solar Farmsolar farm5operational3.0
Drakelowbattery storage1,000application submitted3.0
Mount Road, Castle Gresleybattery storage20approved, not built3.5
Park Roadsolar farm5refused4.8
Park Road, Oversealbattery storage50approved, not built5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7483, -1.642).