Drakelow Solar Farm (5 MW)

Drakelow Solar Farm is a 5 MW solar farm project in South Derbyshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2016; the record was last updated on 1 March 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
1 March 2017record last updated
South Derbyshirecouncil area

Planning timeline

DateStage
8 April 2015Application submitted
24 June 2015Planning permission granted
12 January 2016Construction started
15 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
1 March 2017
Operator or applicant
BlackRock
Planning authority
South Derbyshire
Planning application reference
9/2015/0256
Site area
11.7 ha
Address (REPD)
Land At, Walton Road, Drakelow, Burton-On-Trent, Staffordshire
Council area (by location)
South Derbyshire
Time to decision
11 weeks
REPD reference
5145

Who decides

ApplicationsSouth DerbyshireUK
Decided applications (solar, wind, battery)2610,236
Refused5 (19%)19%
Solar refused4 of 1412%
Battery storage refused1 of 1216%
Median time from submission to decision28.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Caldwell Roadbattery storage90approved, not built1.9
Barn Farm - Batter Energy Storage Facilitybattery storage200approved, not built2.0
Fairfields Energy Storage Systembattery storage1,025approved, not built2.0
Drakelowbattery storage1,000application submitted2.5
Solar Farm & Battery Storage at W/O Rosliston & E/O Walton on Trentsolar farm138approved, not built3.0
Breach Farm Energy Barnbattery storage40approved, not built3.1
Park Roadsolar farm5refused4.2
Brizlincote Hall Solar Farmsolar farm5refused4.4
Mount Road, Castle Gresleybattery storage20approved, not built4.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7742, -1.6535).