Park Road (5 MW solar farm)

Park Road is a 5 MW solar farm project in South Derbyshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 21 April 2016; the record was last updated on 4 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refusedstatus in REPD
4 May 2016record last updated
South Derbyshirecouncil area

Planning timeline

DateStage
1 September 2015Application submitted
21 April 2016Refused by the planning authority

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
4 May 2016
Operator or applicant
Earthworm Energy
Planning authority
South Derbyshire
Planning application reference
9/2015/0689
Site area
13.4 ha
Address (REPD)
LAND AT SK2720, 3150 Park Road, Newhall, Swadlincote
Council area (by location)
South Derbyshire
Time to decision
33 weeks
REPD reference
5806

Who decides

ApplicationsSouth DerbyshireUK
Decided applications (solar, wind, battery)2610,236
Refused5 (19%)19%
Solar refused4 of 1412%
Battery storage refused1 of 1216%
Median time from submission to decision28.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Brizlincote Hall Solar Farmsolar farm5refused1.4
Breach Farm Energy Barnbattery storage40approved, not built1.8
Mount Road, Castle Gresleybattery storage20approved, not built2.3
Lullington Solar Parksolar farm44application submitted2.4
Caldwell Roadbattery storage90approved, not built2.6
Park Road, Oversealbattery storage50approved, not built3.6
Drakelow Solar Farmsolar farm5operational4.2
Newton Solney Solar Farmsolar farm21.1refused4.6
Solar Farm & Battery Storage at W/O Rosliston & E/O Walton on Trentsolar farm138approved, not built4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7785, -1.592).