Energy Projects Near You

Park Road, Overseal (50 MW battery storage)

Park Road, Overseal is a 50 MW battery storage project in South Derbyshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 July 2025, not yet built; the record was last updated on 5 December 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtstatus in REPD
5 December 2025record last updated
South Derbyshirecouncil area

Planning timeline

DateStage
14 October 2024Application submitted
25 July 2025Planning permission granted
25 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
5 December 2025
Operator or applicant
Care Power Overseal
Planning authority
South Derbyshire
Planning application reference
DMPA/2024/1131
Address (REPD)
S/O Park Road, Overseal, Swadlincote
Council area (by location)
South Derbyshire
Time to decision
41 weeks
Name in REPD
Park Road, Overseal - Battery Storage Facility
REPD reference
17586

Who decides

ApplicationsSouth DerbyshireUK
Decided applications (solar, wind, battery)2610,236
Refused5 (19%)19%
Solar refused4 of 1412%
Battery storage refused1 of 1216%
Median time from submission to decision28.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mount Road, Castle Gresleybattery storage20approved, not built2.1
Shortheath Solar Parksolar farm5operational2.4
Lullington Solar Parksolar farm44application submitted2.6
Breach Farm Energy Barnbattery storage40approved, not built3.5
Park Roadsolar farm5refused3.6
Prestop Park Farmsolar farm16operational4.4
Short Hazel Solar Farmsolar farm5operational4.5
Caldwell Roadbattery storage90approved, not built4.6
Brizlincote Hall Solar Farmsolar farm5refused4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7508, -1.5642).