Energy Projects Near You

Prestop Park Farm (16 MW solar farm)

Prestop Park Farm is a 16 MW solar farm project in North West Leicestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 21 March 2015; the record was last updated on 2 May 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16 MWsolar farm
operationalstatus in REPD
2 May 2018record last updated
North West Leicestershirecouncil area

Planning timeline

DateStage
11 July 2014Application submitted
30 September 2014Planning permission granted
26 November 2014Construction started
21 March 2015Operational

Project details

Technology
solar farm
Capacity
16 MW
Status (REPD)
operational
Record last updated
2 May 2018
Operator or applicant
Foresight
Planning authority
North West Leicestershire
Planning application reference
14/00635/FULM
Site area
28.3 ha
Address (REPD)
Prestop Park Farm, Burton Road, Ashby De La Zouch
Council area (by location)
North West Leicestershire
Time to decision
12 weeks
REPD reference
2200

Who decides

ApplicationsNorth West LeicestershireUK
Decided applications (solar, wind, battery)3910,236
Refused2 (5%)19%
Solar refused2 of 3512%
Onshore wind refused0 of 245%
Battery storage refused0 of 216%
Median time from submission to decision12.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

UK: all UK planning authorities. Counted under these REPD planning authority names: Leicestershire, North West Leicestershire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Short Hazel Solar Farmsolar farm5operational2.2
Ashby Solar Farm (a)solar farm5operational3.9
Hill Farm Energy Barnbattery storage10operational4.2
Lullington Solar Parksolar farm44application submitted4.3
Park Road, Oversealbattery storage50approved, not built4.4
Shortheath Solar Parksolar farm5operational4.6
Packington Solar Farmsolar farm13.9operational5.8
Mount Road, Castle Gresleybattery storage20approved, not built6.3
Coalville solar farmsolar farm10abandoned6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7568, -1.499).