Energy Projects Near You

Hill Farm Energy Barn (10 MW battery storage)

Hill Farm Energy Barn is a 10 MW battery storage project in North West Leicestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2017; the record was last updated on 15 March 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWbattery storage
operationalstatus in REPD
15 March 2019record last updated
North West Leicestershirecouncil area

Planning timeline

DateStage
22 June 2016Application submitted
15 December 2016Construction started
31 March 2017Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
10 MW
Status (REPD)
operational
Record last updated
15 March 2019
Operator or applicant
Anesco/ Green Hedge Energy UK
Planning authority
North West Leicestershire
Planning application reference
16/00735/FUL
Address (REPD)
Hill Farm, Spring Lane, Packington, Ashby de la Zouch, Leicestershire
Council area (by location)
North West Leicestershire
Name in REPD
Hill Farm - Energy Barn
REPD reference
6915

Who decides

ApplicationsNorth West LeicestershireUK
Decided applications (solar, wind, battery)3910,236
Refused2 (5%)19%
Solar refused2 of 3512%
Onshore wind refused0 of 245%
Battery storage refused0 of 216%
Median time from submission to decision12.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

UK: all UK planning authorities. Counted under these REPD planning authority names: Leicestershire, North West Leicestershire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Ashby Solar Farm (a)solar farm5operational1.9
Coalville solar farmsolar farm10abandoned2.5
Packington Solar Farmsolar farm13.9operational2.5
Prestop Park Farmsolar farm16operational4.2
Shortheath Solar Parksolar farm5operational6.3
Short Hazel Solar Farmsolar farm5operational6.4
Lane East of Drakelow Roadsolar farm5refused7.2
Park Road, Oversealbattery storage50approved, not built7.5
Lullington Solar Parksolar farm44application submitted8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7279, -1.4589).